Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1998 |
Principal Product | Speaker Cabinets and Plastic Grills |
NAICS | n/a |
SIC | 2499 - Wood Products, Nec |
Sales | n/a |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 4,160 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $32,047 | 458,089 | kWh | $0.07 |
Electricity Fees | $588 | - | $ | - |
Natural Gas | $6,878 | 1,061 | MMBtu | $6.48 |
TOTAL ENERGY COSTS | $93,674 | |||
RECOMMENDED SAVINGS* | $59,740 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $54,183 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,828 Cost: $13,930 |
$4,580 | 67,116 | - | - | - | - | - | - | $248 | - |
$4,580 67,116 kWh |
- - $ |
- - lb |
- - $ |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8112 COMBINE UTILITY METERS |
Savings: $2,565 Cost: $6,000 |
- | - | $2,565 | - | - | - | - | - | - | - |
- - kWh |
$2,565 - $ |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $729 Cost: $2,301 |
$729 | 10,551 | - | - | - | - | - | - | - | - |
$729 10,551 kWh |
- - $ |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $250 Cost: $167 |
$144 | 2,052 | - | - | - | - | $46 | - | $60 | - |
$144 2,052 kWh |
- - $ |
- - lb |
$46 - $ |
$60 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $7,373 Cost: $4,040 |
- | - | - | - | - | - | $7,373 | - | - | - |
- - kWh |
- - $ |
- - lb |
$7,373 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $43,995 Cost: $31,191 |
- | - | - | - | $43,995 | 2,138,400 | - | - | - | - |
- - kWh |
- - $ |
$43,995 2,138,400 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $59,740 Cost: $57,629 |
$5,453 | 79,719 | $2,565 | - | $43,995 | 2,138,400 | $7,419 | - | $308 | - | $5,453 79,719 kWh |
$2,565 - $ |
$43,995 2,138,400 lb |
$7,419 - $ |
$308 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $54,183 Cost: $41,398 |
$144 | 2,052 | $2,565 | - | $43,995 | 2,138,400 | $7,419 | - | $60 | - | $144 2,052 kWh |
$2,565 - $ |
$43,995 2,138,400 lb |
$7,419 - $ |
$60 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Fees | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |