Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1998 |
Principal Product | Computers |
NAICS | n/a |
SIC | 3572 - Computer Storage Devices |
Sales | $100,000,000-$500,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 140,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $158,316 | 5,555,979 | kWh | $0.03 |
Electricity Demand | $121,457 | 12,783 | kW-months/year | $9.50 |
Natural Gas | $107,257 | 27,753 | MMBtu | $3.86 |
TOTAL ENERGY COSTS | $365,853 | |||
RECOMMENDED SAVINGS* | $64,107 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $54,962 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $4,481 Cost: $320 |
- | - | - | - | $4,481 | 1,193 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,481 1,193 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,223 Cost: $837 |
$1,223 | 45,135 | - | - | - | - | - | - | - | - | - | - |
$1,223 45,135 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $846 Cost: $300 |
$456 | 16,706 | $208 | 23 | - | - | - | - | $182 | - | - | - |
$456 16,706 kWh |
$208 23 kW-months/year |
- - MMBtu |
- - lb |
$182 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $728 Cost: $548 |
$445 | 16,413 | $283 | 32 | - | - | - | - | - | - | - | - |
$445 16,413 kWh |
$283 32 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $196 Cost: $329 |
$86 | 3,224 | $130 | 15 | - | - | - | - | - | - | $(-20) | - |
$86 3,224 kWh |
$130 15 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$(-20) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $50,125 Cost: $39,400 |
- | - | - | - | - | - | - | - | $50,125 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$50,125 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $6,348 Cost: - |
- | - | - | - | - | - | - | - | $6,348 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$6,348 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $160 Cost: - |
- | - | - | - | - | - | $160 | 17,651 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$160 17,651 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $64,107 Cost: $41,734 |
$2,210 | 81,478 | $621 | 70 | $4,481 | 1,193 | $160 | 17,651 | $56,655 | - | $(-20) | - | $2,210 81,478 kWh |
$621 70 kW-months/year |
$4,481 1,193 MMBtu |
$160 17,651 lb |
$56,655 - $ |
$(-20) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $54,962 Cost: $40,049 |
$86 | 3,224 | $130 | 15 | $4,481 | 1,193 | $160 | 17,651 | $50,125 | - | $(-20) | - | $86 3,224 kWh |
$130 15 kW-months/year |
$4,481 1,193 MMBtu |
$160 17,651 lb |
$50,125 - $ |
$(-20) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |