IAC Assessment: OK0548
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0548
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1998
Principal Product Livestock Feeds
NAICS n/a
SIC 2048 - Prepared Feeds, Nec
Sales $10,000,000-$50,000,000
# of Employees 30
Plant Area (Sq.Ft.) 80,000
Annual Production 130,000 Tons
Production Hrs. Annual 5,200
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $99,089 3,472,743 kWh $0.03
Electricity Demand $98,441 - kW-months/year -
Electricity Fees $6,064 - $ -
Natural Gas $47,109 11,258 MMBtu $4.18
TOTAL ENERGY COSTS $250,903
RECOMMENDED SAVINGS* $44,457 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,124
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,871
Cost:
$1,728
$1,654 60,961 $1,217 136 - - - - - - - - $1,654
60,961
kWh
$1,217
136
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,968
Cost:
$1,477
$780 28,722 $574 64 - - - - - - $614 - $780
28,722
kWh
$574
64
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
$614
-
$
03: 2.6232 INSTALL SET-BACK TIMERS Savings:
$1,164
Cost:
$146
- - - - $1,164 288 - - - - - - -
-
kWh
-
-
kW-months/year
$1,164
288
MMBtu
-
-
lb
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,020
Cost:
$400
$1,020 37,515 - - - - - - - - - - $1,020
37,515
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,104
Cost:
$1,566
$1,104 37,808 - - - - - - - - - - $1,104
37,808
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
06: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$34,130
Cost:
$12,800
- - - - - - - - $8,130 - $26,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$8,130
-
$
$26,000
-
$
07: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$2,200
Cost:
$6,000
- - - - - - $2,200 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$2,200
-
lb
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$44,457
Cost:
$24,117
$4,558 165,006 $1,791 200 $1,164 288 $2,200 - $8,130 - $26,614 - $4,558
165,006
kWh
$1,791
200
kW-months/year
$1,164
288
MMBtu
$2,200
-
lb
$8,130
-
$
$26,614
-
$
TOTAL IMPLEMENTED Savings:
$2,124
Cost:
$1,966
$2,124 75,323 - - - - - - - - - - $2,124
75,323
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Personnel Changes Ancillary Material Cost