IAC Assessment: OK0602
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0602
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2000
Principal Product Vinyl flooring
NAICS n/a
SIC 3996 - Hard Surface Floor Coverings, Nec
Sales $50,000,000-$100,000,000
# of Employees 180
Plant Area (Sq.Ft.) 435,000
Annual Production 42,000,000 Thousand Feet
Production Hrs. Annual 8,760
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $902,876 24,038,394 kWh $0.04
Electricity Fees $3,538 - $ -
Natural Gas $571,959 226,827 MMBtu $2.52
TOTAL ENERGY COSTS $2,081,873
RECOMMENDED SAVINGS* $413,796 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $15,151
#|Description Savings
Cost
Status Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes
$ kWh $ MMBtu $ lb $ $
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$15,151
Cost:
$14,545
$15,151 402,989 - - - - - - $15,151
402,989
kWh
-
-
MMBtu
-
-
lb
-
-
$
02: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT Savings:
$2,001
Cost:
$10,500
- - $2,001 735 - - - - -
-
kWh
$2,001
735
MMBtu
-
-
lb
-
-
$
03: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING Savings:
$26,183
Cost:
$35,000
$26,183 696,366 - - - - - - $26,183
696,366
kWh
-
-
MMBtu
-
-
lb
-
-
$
04: 2.7145 INSTALL SKYLIGHTS Savings:
$9,262
Cost:
$5,460
$9,262 246,483 - - - - - - $9,262
246,483
kWh
-
-
MMBtu
-
-
lb
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$276
Cost:
$1,620
$276 7,327 - - - - - - $276
7,327
kWh
-
-
MMBtu
-
-
lb
-
-
$
06: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$229,950
Cost:
$32,400
- - - - - - $229,950 - -
-
kWh
-
-
MMBtu
-
-
lb
$229,950
-
$
07: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$122,640
Cost:
$200,000
- - - - - - $122,640 - -
-
kWh
-
-
MMBtu
-
-
lb
$122,640
-
$
08: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$8,333
Cost:
-
- - - - $8,333 40,000 - - -
-
kWh
-
-
MMBtu
$8,333
40,000
lb
-
-
$
TOTAL RECOMMENDED Savings:
$413,796
Cost:
$299,525
$50,872 1,353,165 $2,001 735 $8,333 40,000 $352,590 - $50,872
1,353,165
kWh
$2,001
735
MMBtu
$8,333
40,000
lb
$352,590
-
$
TOTAL IMPLEMENTED Savings:
$15,151
Cost:
$14,545
$15,151 402,989 - - - - - - $15,151
402,989
kWh
-
-
MMBtu
-
-
lb
-
-
$
Savings
Cost
$ kWh $ MMBtu $ lb $ $
Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes Electricity Usage Natural Gas Solid Waste (non-haz) Personnel Changes