IAC Assessment: OK0618
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0618
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2001
Principal Product Pre-cut Produce
NAICS n/a
SIC 2099 - Food Preparations, Nec
Sales $5,000,000-$10,000,000
# of Employees 80
Plant Area (Sq.Ft.) 35,000
Annual Production 10,000,000 Pounds
Production Hrs. Annual 3,600
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $29,043 927,125 kWh $0.03
Electricity Demand $23,782 232 kW-months/year $102.51
Electricity Fees $8,834 - $ -
Natural Gas $3,144 1,196 MMBtu $2.63
TOTAL ENERGY COSTS $69,003
RECOMMENDED SAVINGS* $38,820 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,819
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,359
Cost:
$4,547
$734 23,315 $506 5 - - - - - - $119 - $734
23,315
kWh
$506
5
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
$119
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$542
Cost:
$1,523
$542 17,585 - - - - - - - - - - $542
17,585
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
03: 2.6232 INSTALL SET-BACK TIMERS Savings:
$4,260
Cost:
$385
- - - - $4,260 461 - - - - - - -
-
kWh
-
-
kW-months/year
$4,260
461
MMBtu
-
-
Tgal
-
-
$
-
-
$
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$459
Cost:
$140
$459 14,920 - - - - - - - - - - $459
14,920
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
05: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$28,000
Cost:
-
- - - - - - - - $28,000 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$28,000
-
$
-
-
$
06: 3.1293 SEPARATE TREATMENTS FOR EACH TYPE OF SOLUTION AND RECYCLE Savings:
$4,200
Cost:
-
- - - - - - $4,200 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$4,200
-
Tgal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$38,820
Cost:
$6,595
$1,735 55,820 $506 5 $4,260 461 $4,200 - $28,000 - $119 - $1,735
55,820
kWh
$506
5
kW-months/year
$4,260
461
MMBtu
$4,200
-
Tgal
$28,000
-
$
$119
-
$
TOTAL IMPLEMENTED Savings:
$9,819
Cost:
$4,932
$734 23,315 $506 5 $4,260 461 $4,200 - - - $119 - $734
23,315
kWh
$506
5
kW-months/year
$4,260
461
MMBtu
$4,200
-
Tgal
-
-
$
$119
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost