Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2001 |
Principal Product | Plastic Packaging |
NAICS | n/a |
SIC | 2899 - Chemical Preparations, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 175,000 |
Annual Production | 68,000,000 Pounds |
Production Hrs. Annual | 8,760 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $855,741 | 34,464,000 | kWh | $0.02 |
Electricity Demand | $343,244 | 55,970 | kW-months/year | $6.13 |
Electricity Fees | $282,984 | - | $ | - |
Natural Gas | $17,779 | 3,012 | MMBtu | $5.90 |
TOTAL ENERGY COSTS | $1,473,748 | |||
RECOMMENDED SAVINGS* | $178,232 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $99,653 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $792 Cost: $310 |
$82 | 3,294 | $28 | 5 | - | - | - | - | $168 | - | - | - | $514 | - |
$82 3,294 kWh |
$28 5 kW-months/year |
- - MMBtu |
- - gal |
$168 - $ |
- - $ |
$514 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,585 Cost: $18,400 |
$1,974 | 79,609 | $828 | 135 | - | - | - | - | - | - | - | - | $2,783 | - |
$1,974 79,609 kWh |
$828 135 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
$2,783 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $816 Cost: $878 |
$816 | 32,890 | - | - | - | - | - | - | - | - | - | - | - | - |
$816 32,890 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,184 Cost: $200 |
$2,453 | 98,910 | $831 | 136 | - | - | - | - | $(-100) | - | - | - | - | - |
$2,453 98,910 kWh |
$831 136 kW-months/year |
- - MMBtu |
- - gal |
$(-100) - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $1,191 Cost: $1,423 |
$891 | 35,916 | $300 | 49 | - | - | - | - | - | - | - | - | - | - |
$891 35,916 kWh |
$300 49 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.3125 USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS |
Savings: $38,340 Cost: $12,500 |
- | - | - | - | - | - | $38,340 | 4,810 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$38,340 4,810 gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7242 CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES |
Savings: $68,500 Cost: $15,000 |
$68,500 | 2,761,986 | - | - | - | - | - | - | - | - | - | - | - | - |
$68,500 2,761,986 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE |
Savings: $2,200 Cost: $1,326 |
- | - | $2,200 | 360 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$2,200 360 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,082 Cost: $3,936 |
$2,303 | 92,856 | $779 | 127 | - | - | - | - | - | - | - | - | - | - |
$2,303 92,856 kWh |
$779 127 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $12,577 Cost: $3,000 |
$1,013 | 40,827 | - | - | $11,564 | 1,500 | - | - | - | - | - | - | - | - |
$1,013 40,827 kWh |
- - kW-months/year |
$11,564 1,500 MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $11,523 Cost: $10,275 |
$8,610 | 347,170 | $2,913 | 475 | - | - | - | - | - | - | - | - | - | - |
$8,610 347,170 kWh |
$2,913 475 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.114 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS |
Savings: $29,565 Cost: $10,000 |
- | - | - | - | - | - | - | - | $29,565 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$29,565 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $877 Cost: - |
- | - | - | - | - | - | - | - | - | - | $877 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
$877 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $178,232 Cost: $77,248 |
$86,642 | 3,493,458 | $7,879 | 1,287 | $11,564 | 1,500 | $38,340 | 4,810 | $29,633 | - | $877 | - | $3,297 | - | $86,642 3,493,458 kWh |
$7,879 1,287 kW-months/year |
$11,564 1,500 MMBtu |
$38,340 4,810 gal |
$29,633 - $ |
$877 - $ |
$3,297 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $99,653 Cost: $30,111 |
$80,658 | 3,252,187 | $5,972 | 976 | $11,564 | 1,500 | - | - | $68 | - | $877 | - | $514 | - | $80,658 3,252,187 kWh |
$5,972 976 kW-months/year |
$11,564 1,500 MMBtu |
- - gal |
$68 - $ |
$877 - $ |
$514 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |