IAC Assessment: OK0651
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0651
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2002
Principal Product Electric winches
NAICS n/a
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $10,000,000-$50,000,000
# of Employees 150
Plant Area (Sq.Ft.) 127,000
Annual Production 40,000 Pieces
Production Hrs. Annual 4,420
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $164,930 2,958,800 kWh $0.06
Electricity Demand $873 - kW-months/year -
Electricity Fees $2,656 - $ -
Natural Gas $54,029 7,945 MMBtu $6.80
TOTAL ENERGY COSTS $304,976
RECOMMENDED SAVINGS* $277,006 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ MMBtu $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$7,419
Cost:
$20,491
$3,888 69,805 - - - - $3,531 - $3,888
69,805
kWh
-
-
MMBtu
-
-
$
$3,531
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,926
Cost:
$1,360
$6,326 113,573 - - $(-400) - - - $6,326
113,573
kWh
-
-
MMBtu
$(-400)
-
$
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,142
Cost:
$2,300
$1,142 20,509 - - - - - - $1,142
20,509
kWh
-
-
MMBtu
-
-
$
-
-
$
04: 2.7141 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS Savings:
$131,274
Cost:
$26,000
- - - - $131,274 - - - -
-
kWh
-
-
MMBtu
$131,274
-
$
-
-
$
05: 2.6232 INSTALL SET-BACK TIMERS Savings:
$10,697
Cost:
$1,416
- - $10,697 1,161 - - - - -
-
kWh
$10,697
1,161
MMBtu
-
-
$
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$741
Cost:
$975
$741 13,304 - - - - - - $741
13,304
kWh
-
-
MMBtu
-
-
$
-
-
$
07: 4.4240 IMPROVE SPACE COMFORT CONDITIONING Savings:
$37,907
Cost:
$36,300
$1,897 34,056 - - $36,010 - - - $1,897
34,056
kWh
-
-
MMBtu
$36,010
-
$
-
-
$
08: 4.5130 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$11,700
Cost:
$1,350
- - - - $11,700 - - - -
-
kWh
-
-
MMBtu
$11,700
-
$
-
-
$
09: 4.3210 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES Savings:
$23,400
Cost:
$80,000
- - - - $23,400 - - - -
-
kWh
-
-
MMBtu
$23,400
-
$
-
-
$
10: 4.4240 IMPROVE SPACE COMFORT CONDITIONING Savings:
$46,800
Cost:
$2,500
- - - - $46,800 - - - -
-
kWh
-
-
MMBtu
$46,800
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$277,006
Cost:
$172,692
$13,994 251,247 $10,697 1,161 $248,784 - $3,531 - $13,994
251,247
kWh
$10,697
1,161
MMBtu
$248,784
-
$
$3,531
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Natural Gas Personnel Changes Ancillary Material Cost