Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2004 |
Principal Product | Plastic Cups and Plates |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 265,200 |
Annual Production | 10,200,000 Pieces |
Production Hrs. Annual | 8,000 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,472,064 | 39,962,400 | kWh | $0.04 |
Natural Gas | $38,149 | 5,405 | MMBtu | $7.06 |
TOTAL ENERGY COSTS | $1,522,453 | |||
RECOMMENDED SAVINGS* | $144,607 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,978 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $22,584 Cost: $52,597 |
$19,311 | 524,768 | - | - | - | - | - | - | $3,273 | - | - | - |
$19,311 524,768 kWh |
- - MMBtu |
- - $ |
- - $ |
$3,273 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,824 Cost: $980 |
$170 | 4,608 | - | - | $531 | - | - | - | $2,123 | - | - | - |
$170 4,608 kWh |
- - MMBtu |
$531 - $ |
- - $ |
$2,123 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $26,433 Cost: $1,100 |
- | - | $26,433 | 3,744 | - | - | - | - | - | - | - | - |
- - kWh |
$26,433 3,744 MMBtu |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING |
Savings: $19,697 Cost: $15,783 |
- | - | $19,697 | 2,790 | - | - | - | - | - | - | - | - |
- - kWh |
$19,697 2,790 MMBtu |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $3,154 Cost: $590 |
- | - | - | - | - | - | $3,154 | - | - | - | - | - |
- - kWh |
- - MMBtu |
- - $ |
$3,154 - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $21,427 Cost: $28,713 |
$21,427 | 582,253 | - | - | - | - | - | - | - | - | - | - |
$21,427 582,253 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.5123 REDUCE FLUID FLOW RATES |
Savings: $38,434 Cost: $27,594 |
$38,434 | 1,044,400 | - | - | - | - | - | - | - | - | - | - |
$38,434 1,044,400 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $945 Cost: $479 |
$945 | 25,728 | - | - | - | - | - | - | - | - | - | - |
$945 25,728 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4141 REPLACE THE CHLORINATION STAGE WITH AN OXYGEN OR OZONE STAGE |
Savings: $9,109 Cost: $36,000 |
$(-618) | (-16,781) | - | - | - | - | - | - | - | - | $9,727 | - |
$(-618) (-16,781) kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
$9,727 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $144,607 Cost: $163,836 |
$79,669 | 2,164,976 | $46,130 | 6,534 | $531 | - | $3,154 | - | $5,396 | - | $9,727 | - | $79,669 2,164,976 kWh |
$46,130 6,534 MMBtu |
$531 - $ |
$3,154 - $ |
$5,396 - $ |
$9,727 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,978 Cost: $1,570 |
$170 | 4,608 | - | - | $531 | - | $3,154 | - | $2,123 | - | - | - | $170 4,608 kWh |
- - MMBtu |
$531 - $ |
$3,154 - $ |
$2,123 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Water Consumption |