Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2005 |
Principal Product | Commercial aggregate |
NAICS | 327991 - Cut Stone and Stone Product Manufacturing |
SIC | 3281 - Cut Stone And Stone Products |
Sales | $1,000,000-$5,000,000 |
# of Employees | 31 |
Plant Area (Sq.Ft.) | 1,000,000 |
Annual Production | 1,900,000 Tons |
Production Hrs. Annual | 5,824 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $191,173 | 5,511,600 | kWh | $0.03 |
Electricity Demand | $158,115 | 23,302 | kW-months/year | $6.79 |
Electricity Fees | $(-31,658) | - | $ | - |
TOTAL ENERGY COSTS | $317,630 | |||
RECOMMENDED SAVINGS* | $(-13,244) | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Personnel Changes | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Fuel Oil #2 | Personnel Changes | Ancillary Material Cost | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $10,863 Cost: $38,544 |
- | - | $10,863 | 1,908 | - | - | - | - | - | - | - | - |
- - kWh |
$10,863 1,908 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $1,900 Cost: $200 |
- | - | - | - | - | - | $1,900 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,900 - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $(-28,676) Cost: - |
$(-15,087) | (-434,785) | - | - | $(-13,599) | (-806) | - | - | - | - | $10 | - |
$(-15,087) (-434,785) kWh |
- - kW-months/year |
$(-13,599) (-806) MMBtu |
- - $ |
- - $ |
$10 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,725 Cost: $125 |
$1,041 | 30,000 | $684 | 120 | - | - | - | - | - | - | - | - |
$1,041 30,000 kWh |
$684 120 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $212 Cost: $475 |
$212 | 6,124 | - | - | - | - | - | - | - | - | - | - |
$212 6,124 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $579 Cost: $25 |
$579 | 16,697 | - | - | - | - | - | - | - | - | - | - |
$579 16,697 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $153 Cost: $1,346 |
$92 | 2,662 | $70 | 12 | - | - | - | - | $(-9) | - | - | - |
$92 2,662 kWh |
$70 12 kW-months/year |
- - MMBtu |
- - $ |
$(-9) - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $(-13,244) Cost: $40,715 |
$(-13,163) | (-379,302) | $11,617 | 2,040 | $(-13,599) | (-806) | $1,900 | - | $(-9) | - | $10 | - | $(-13,163) (-379,302) kWh |
$11,617 2,040 kW-months/year |
$(-13,599) (-806) MMBtu |
$1,900 - $ |
$(-9) - $ |
$10 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Personnel Changes | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Fuel Oil #2 | Personnel Changes | Ancillary Material Cost | Increase in Production |