Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2006 |
Principal Product | Metal Plating |
NAICS | 332811 - Metal Heat Treating |
SIC | 3471 - Plating And Polishing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 70,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | OK |
View Case Study |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $297,576 | 6,071,609 | kWh | $0.05 |
Electricity Demand | $77,096 | 16,966 | kW-months/year | $4.54 |
Electricity Fees | $5,303 | - | $ | - |
Natural Gas | $200,899 | 32,308 | MMBtu | $6.22 |
TOTAL ENERGY COSTS | $640,327 | |||
RECOMMENDED SAVINGS* | $86,383 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $65,238 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1212 OPERATE BOILERS ON HIGH FIRE SETTING |
Savings: $23,600 Cost: $18,000 |
- | - | - | - | $23,600 | 3,077 | - | - |
- - kWh |
- - kW-months/year |
$23,600 3,077 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $7,849 Cost: $10,033 |
- | - | - | - | $7,849 | 1,023 | - | - |
- - kWh |
- - kW-months/year |
$7,849 1,023 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING |
Savings: $1,135 Cost: $587 |
- | - | - | - | $1,135 | 148 | - | - |
- - kWh |
- - kW-months/year |
$1,135 148 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $1,065 Cost: $2,539 |
- | - | - | - | $1,065 | 139 | - | - |
- - kWh |
- - kW-months/year |
$1,065 139 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $3,531 Cost: $5,250 |
- | - | - | - | $3,531 | 460 | - | - |
- - kWh |
- - kW-months/year |
$3,531 460 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $13,876 Cost: $17,879 |
$13,876 | 221,654 | - | - | - | - | - | - |
$13,876 221,654 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $8,395 Cost: $7,192 |
$8,395 | 149,174 | - | - | - | - | - | - |
$8,395 149,174 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $23,096 Cost: $42,002 |
$23,096 | 368,945 | - | - | - | - | - | - |
$23,096 368,945 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,836 Cost: $9,913 |
$3,577 | 73,008 | $531 | 117 | - | - | $(-272) | - |
$3,577 73,008 kWh |
$531 117 kW-months/year |
- - MMBtu |
$(-272) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $86,383 Cost: $113,395 |
$48,944 | 812,781 | $531 | 117 | $37,180 | 4,847 | $(-272) | - | $48,944 812,781 kWh |
$531 117 kW-months/year |
$37,180 4,847 MMBtu |
$(-272) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $65,238 Cost: $83,718 |
$36,972 | 590,599 | - | - | $28,266 | 3,685 | - | - | $36,972 590,599 kWh |
- - kW-months/year |
$28,266 3,685 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |