IAC logo
IAC Assessment: OK0731
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0731
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2006
Principal Product Truck
NAICS 336120 - Heavy Duty Truck Manufacturing
SIC 3713 - Truck And Bus Bodies
Sales $10,000,000-$50,000,000
# of Employees 260
Plant Area (Sq.Ft.) 500,000
Annual Production 450 Units
Production Hrs. Annual 4,160
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $240,591 5,602,800 kWh $0.04
Electricity Demand $92,496 15,080 kW-months/year $6.13
Electricity Fees $1,711 - $ -
Natural Gas $276,108 30,296 MMBtu $9.11
TOTAL ENERGY COSTS $619,157
RECOMMENDED SAVINGS* $119,207 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,099
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.9113 USE SOLAR HEAT FOR HEAT Savings:
$97,944
Cost:
$80,060
- - $97,944 10,747 -
-
kWh
$97,944
10,747
MMBtu
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$6,213
Cost:
-
- - $6,213 682 -
-
kWh
$6,213
682
MMBtu
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$5,514
Cost:
$3,851
- - $5,514 605 -
-
kWh
$5,514
605
MMBtu
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,650
Cost:
$9,975
$2,650 61,765 - - $2,650
61,765
kWh
-
-
MMBtu
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,071
Cost:
$3,949
$1,071 24,960 - - $1,071
24,960
kWh
-
-
MMBtu
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$732
Cost:
$727
$732 18,189 - - $732
18,189
kWh
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,083
Cost:
$68,849
$5,083 100,398 - - $5,083
100,398
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$119,207
Cost:
$167,411
$9,536 205,312 $109,671 12,034 $9,536
205,312
kWh
$109,671
12,034
MMBtu
TOTAL IMPLEMENTED Savings:
$13,099
Cost:
$73,525
$6,886 143,547 $6,213 682 $6,886
143,547
kWh
$6,213
682
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas