Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2008 |
Principal Product | Customized rubber and plastic |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 45 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 600,000 Pounds |
Production Hrs. Annual | 2,080 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $157,667 | 2,200,800 | kWh | $0.07 |
Natural Gas | $129,922 | 15,483 | MMBtu | $8.39 |
TOTAL ENERGY COSTS | $287,589 | |||
RECOMMENDED SAVINGS* | $72,878 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,109 Cost: $5,086 |
- | - | $3,109 | 370 |
- - kWh |
$3,109 370 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,596 Cost: $14,878 |
$1,596 | 29,390 | - | - |
$1,596 29,390 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $477 Cost: $1,165 |
$477 | 4,836 | - | - |
$477 4,836 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $22,038 Cost: $14,300 |
- | - | $22,038 | 2,623 |
- - kWh |
$22,038 2,623 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $7,000 Cost: - |
$7,000 | - | - | - |
$7,000 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2153 CLOSE OFF UNNEEDED STEAM LINES |
Savings: $7,161 Cost: - |
- | - | $7,161 | 854 |
- - kWh |
$7,161 854 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $28,620 Cost: $23,375 |
- | - | $28,620 | 2,729 |
- - kWh |
$28,620 2,729 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1241 REDUCE EXCESSIVE BOILER BLOWDOWN |
Savings: $2,877 Cost: - |
- | - | $2,877 | 343 |
- - kWh |
$2,877 343 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $72,878 Cost: $58,804 |
$9,073 | 34,226 | $63,805 | 6,919 | $9,073 34,226 kWh |
$63,805 6,919 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |