Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2010 |
Principal Product | Batteries |
NAICS | 335911 - Storage Battery Manufacturing |
SIC | 3692 - Primary Batteries, Dry And Wet |
Sales | $50,000,000-$100,000,000 |
# of Employees | 206 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 421,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,094,155 | 21,945,600 | kWh | $0.05 |
Natural Gas | $495,376 | 72,602 | MMBtu | $6.82 |
TOTAL ENERGY COSTS | $1,589,531 | |||
RECOMMENDED SAVINGS* | $124,517 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $57,362 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $285 Cost: $451 |
- | - | $285 | 42 |
- - kWh |
$285 42 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING |
Savings: $29,667 Cost: $2,587 |
- | - | $29,667 | 4,350 |
- - kWh |
$29,667 4,350 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING |
Savings: $1,568 Cost: $1,078 |
- | - | $1,568 | 230 |
- - kWh |
$1,568 230 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1135 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY |
Savings: $3,625 Cost: $1,176 |
- | - | $3,625 | 532 |
- - kWh |
$3,625 532 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,103 Cost: $5,543 |
$1,103 | 22,117 | - | - |
$1,103 22,117 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,350 Cost: $8,818 |
$2,350 | 47,129 | - | - |
$2,350 47,129 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $35,265 Cost: $98,109 |
$35,265 | 707,317 | - | - |
$35,265 707,317 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $441 Cost: $1,170 |
$441 | 8,833 | - | - |
$441 8,833 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,877 Cost: - |
$5,877 | 117,540 | - | - |
$5,877 117,540 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $15,837 Cost: $12,000 |
$15,837 | 303,085 | - | - |
$15,837 303,085 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $6,106 Cost: $101,906 |
$6,106 | 122,129 | - | - |
$6,106 122,129 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $22,393 Cost: $7,656 |
$22,393 | 447,861 | - | - |
$22,393 447,861 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $124,517 Cost: $240,494 |
$89,372 | 1,776,011 | $35,145 | 5,154 | $89,372 1,776,011 kWh |
$35,145 5,154 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $57,362 Cost: $120,554 |
$53,452 | 1,057,531 | $3,910 | 574 | $53,452 1,057,531 kWh |
$3,910 574 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |