Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2012 |
Principal Product | Health care |
NAICS | 622110 - General Medical and Surgical Hospitals |
SIC | 8062 - General Medical & Surgical Hospitals |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 230,000 |
Annual Production | 144 Units |
Production Hrs. Annual | 8,760 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $516,606 | 9,618,032 | kWh | $0.05 |
Electricity Demand | $153,117 | 16,289 | kW-months/year | $9.40 |
Natural Gas | $112,755 | 22,090 | MMBtu | $5.10 |
TOTAL ENERGY COSTS | $782,478 | |||
RECOMMENDED SAVINGS* | $134,205 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $28,523 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS |
Savings: $65,995 Cost: $22,579 |
$65,995 | 970,515 | - | - | - | - |
$65,995 970,515 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7211 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS |
Savings: $17,278 Cost: $4,230 |
$10,578 | 155,675 | $6,700 | 713 | - | - |
$10,578 155,675 kWh |
$6,700 713 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,738 Cost: $575 |
- | - | - | - | $1,738 | 341 |
- - kWh |
- - kW-months/year |
$1,738 341 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,034 Cost: $7,088 |
$1,034 | 15,211 | - | - | - | - |
$1,034 15,211 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $670 Cost: $4,525 |
$670 | 9,855 | - | - | - | - |
$670 9,855 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,402 Cost: $2,482 |
$1,041 | 15,321 | $361 | 38 | - | - |
$1,041 15,321 kWh |
$361 38 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1224 REPLACE BOILER |
Savings: $34,401 Cost: $192,000 |
- | - | - | - | $34,401 | 6,745 |
- - kWh |
- - kW-months/year |
$34,401 6,745 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $8,797 Cost: $18,000 |
- | - | - | - | $8,797 | 1,725 |
- - kWh |
- - kW-months/year |
$8,797 1,725 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $678 Cost: $1,689 |
- | - | - | - | $678 | 133 |
- - kWh |
- - kW-months/year |
$678 133 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,778 Cost: $1,400 |
$1,778 | 26,140 | - | - | - | - |
$1,778 26,140 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $434 Cost: $1,575 |
$434 | 6,376 | - | - | - | - |
$434 6,376 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $134,205 Cost: $256,143 |
$81,530 | 1,199,093 | $7,061 | 751 | $45,614 | 8,944 | $81,530 1,199,093 kWh |
$7,061 751 kW-months/year |
$45,614 8,944 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $28,523 Cost: $28,155 |
$13,026 | 191,670 | $6,700 | 713 | $8,797 | 1,725 | $13,026 191,670 kWh |
$6,700 713 kW-months/year |
$8,797 1,725 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |