IAC Assessment: OK0879
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0879
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2014
Principal Product Electric Motors, Water systems, Fueling systems
NAICS 335312 - Motor and Generator Manufacturing
SIC 3621 - Motors And Generators
Sales $50,000,000-$100,000,000
# of Employees 335
Plant Area (Sq.Ft.) 332,000
Annual Production 75,000 Pieces
Production Hrs. Annual 4,810
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $525,016 10,224,900 kWh $0.05
Electricity Demand $161,573 19,350 kW-months/year $8.35
Natural Gas $133,393 22,191 MMBtu $6.01
TOTAL ENERGY COSTS $819,981
RECOMMENDED SAVINGS* $305,581 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $39,189
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$18,268
Cost:
$1,245
$18,268 356,111 - - - - - - $18,268
356,111
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
02: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$6,423
Cost:
$7,826
$6,423 125,195 - - - - - - $6,423
125,195
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,769
Cost:
$168
$3,769 73,474 - - - - - - $3,769
73,474
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
04: 2.7211 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS Savings:
$1,649
Cost:
$1,014
$839 16,351 $810 97 - - - - $839
16,351
kWh
$810
97
kW-months/year
-
-
$
-
-
MMBtu
05: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$39,930
Cost:
$127,500
- - - - - - $39,930 6,643 -
-
kWh
-
-
kW-months/year
-
-
$
$39,930
6,643
MMBtu
06: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$8,374
Cost:
$29,700
$(-1,003) (-19,551) - - - - $9,377 1,560 $(-1,003)
(-19,551)
kWh
-
-
kW-months/year
-
-
$
$9,377
1,560
MMBtu
07: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$3,751
Cost:
$6,500
- - - - - - $3,751 624 -
-
kWh
-
-
kW-months/year
-
-
$
$3,751
624
MMBtu
08: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$402
Cost:
$237
$402 7,834 - - - - - - $402
7,834
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
09: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$29,530
Cost:
$21,500
$(-154) (-3,004) - - - - $29,684 4,938 $(-154)
(-3,004)
kWh
-
-
kW-months/year
-
-
$
$29,684
4,938
MMBtu
10: 2.2511 INSULATE BARE EQUIPMENT Savings:
$304
Cost:
$148
$304 5,923 - - - - - - $304
5,923
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
11: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$332
Cost:
$3,829
$332 6,478 - - - - - - $332
6,478
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
12: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$587
Cost:
$5,092
$587 11,445 - - - - - - $587
11,445
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
13: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$600
Cost:
$7,371
$600 11,697 - - - - - - $600
11,697
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
14: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$36,208
Cost:
$5,120
$36,208 705,810 - - - - - - $36,208
705,810
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
15: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$155,454
Cost:
-
- - - - $155,454 - - - -
-
kWh
-
-
kW-months/year
$155,454
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$305,581
Cost:
$217,250
$66,575 1,297,763 $810 97 $155,454 - $82,742 13,765 $66,575
1,297,763
kWh
$810
97
kW-months/year
$155,454
-
$
$82,742
13,765
MMBtu
TOTAL IMPLEMENTED Savings:
$39,189
Cost:
$40,338
$29,002 565,337 $810 97 - - $9,377 1,560 $29,002
565,337
kWh
$810
97
kW-months/year
-
-
$
$9,377
1,560
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas