Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2014 |
Principal Product | Hydraulic lift tables for material handling |
NAICS | 333923 - Overhead Traveling Crane, Hoist, and Monorail System Manufacturing |
SIC | 3559 - Special Industry Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 114,750 |
Annual Production | 20,000 Pieces |
Production Hrs. Annual | 4,940 |
Location (State) | AR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $74,955 | 1,626,720 | kWh | $0.05 |
Electricity Demand | $43,998 | 5,378 | kW-months/year | $8.18 |
Natural Gas | $39,370 | 5,124 | MMBtu | $7.68 |
TOTAL ENERGY COSTS | $158,323 | |||
RECOMMENDED SAVINGS* | $29,877 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,877 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $5,056 Cost: - |
- | - | - | - | $5,056 | - |
- - kWh |
- - MMBtu |
$5,056 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,440 Cost: $1,188 |
$2,440 | 52,944 | - | - | - | - |
$2,440 52,944 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,796 Cost: $2,066 |
- | - | $2,796 | 364 | - | - |
- - kWh |
$2,796 364 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION |
Savings: $248 Cost: - |
$248 | 5,375 | - | - | - | - |
$248 5,375 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,000 Cost: $10,067 |
$3,000 | 65,075 | - | - | - | - |
$3,000 65,075 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,792 Cost: $1,656 |
$2,792 | 60,570 | - | - | - | - |
$2,792 60,570 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $13,545 Cost: $3,641 |
- | - | $13,545 | 1,764 | - | - |
- - kWh |
$13,545 1,764 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,877 Cost: $18,618 |
$8,480 | 183,964 | $16,341 | 2,128 | $5,056 | - | $8,480 183,964 kWh |
$16,341 2,128 MMBtu |
$5,056 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,877 Cost: $18,618 |
$8,480 | 183,964 | $16,341 | 2,128 | $5,056 | - | $8,480 183,964 kWh |
$16,341 2,128 MMBtu |
$5,056 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |