TOP | ARC | Description | Recommendations Reccs | Recommended $ Savings | Average Payback (yrs) | Implementation Rate Imp Rate | |
---|---|---|---|---|---|---|---|
back | 2.xxxx | 2.xxxx ENERGY MANAGEMENT | 136,285 | $1,861,769,515 | 1.8 | 51.0% | |
back | 2.6xxx | 2.6xxx Operations | 7,046 | $57,813,904 | 0.6 | 55.3% | |
back | 2.62xx | 2.62xx EQUIPMENT CONTROL | 6,450 | $54,071,096 | 0.6 | 54.2% | |
2.624x | 2.624x Load Reduction | 178 | $2,278,959 | 0.7 | 49.1% | ||
2.6241 | 2.6241 REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | 47 | $376,258 | 0.7 | 43.5% | ||
2.6242 | 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | 131 | $1,902,701 | 0.7 | 51.2% |