IAC Assessment: OK0905
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0905
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2015
Principal Product Oil field equipment
NAICS 333132 - Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533 - Oil And Gas Field Machinery
Sales $10,000,000-$50,000,000
# of Employees 96
Plant Area (Sq.Ft.) 92,700
Annual Production 50 Pieces
Production Hrs. Annual 3,250
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $72,156 907,882 kWh $0.08
Natural Gas $34,023 5,011 MMBtu $6.79
TOTAL ENERGY COSTS $106,179
RECOMMENDED SAVINGS* $26,758 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,534
Cost:
$2,400
$3,534 44,732 - - $3,534
44,732
kWh
-
-
MMBtu
02: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$98
Cost:
$77
$98 1,236 - - $98
1,236
kWh
-
-
MMBtu
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$146
Cost:
$463
$146 1,848 - - $146
1,848
kWh
-
-
MMBtu
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$468
Cost:
$1,220
- - $468 69 -
-
kWh
$468
69
MMBtu
05: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$1,180
Cost:
$2,817
$1,180 14,944 - - $1,180
14,944
kWh
-
-
MMBtu
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$920
Cost:
$2,441
$920 11,641 - - $920
11,641
kWh
-
-
MMBtu
07: 2.7134 USE PHOTOCELL CONTROLS Savings:
$2,888
Cost:
$3,680
$2,888 36,551 - - $2,888
36,551
kWh
-
-
MMBtu
08: 2.7122 DISCONNECT BALLASTS Savings:
$627
Cost:
$144
$627 7,933 - - $627
7,933
kWh
-
-
MMBtu
09: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$296
Cost:
$476
$296 3,744 - - $296
3,744
kWh
-
-
MMBtu
10: 2.6232 INSTALL SET-BACK TIMERS Savings:
$3,337
Cost:
$192
$2,896 37,122 $441 65 $2,896
37,122
kWh
$441
65
MMBtu
11: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$8,784
Cost:
$8,940
$10,957 138,691 $(-2,173) (-320) $10,957
138,691
kWh
$(-2,173)
(-320)
MMBtu
12: 4.623 EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME Savings:
$1,749
Cost:
$1,248
$1,749 22,136 - - $1,749
22,136
kWh
-
-
MMBtu
13: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,731
Cost:
$8,268
$2,731 34,567 - - $2,731
34,567
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$26,758
Cost:
$32,366
$28,021 355,145 $(-1,263) (-186) $28,021
355,145
kWh
$(-1,263)
(-186)
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas