Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2021 |
Principal Product | Architectural fencing |
NAICS | 332323 - Ornamental and Architectural Metal Work Manufacturing |
SIC | 3446 - Architectural Metal Work |
Sales | $100,000,000-$500,000,000 |
# of Employees | 523 |
Plant Area (Sq.Ft.) | 696,530 |
Annual Production | 60,000 Tons |
Production Hrs. Annual | 2,340 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $994,163 | 18,757,788 | kWh | $0.05 |
Electricity Demand | $464,296 | 58,402 | kW-months/year | $7.95 |
Natural Gas | $464,451 | 171,384 | MMBtu | $2.71 |
TOTAL ENERGY COSTS | $1,922,910 | |||
RECOMMENDED SAVINGS* | $114,669 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,075 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $83,427 Cost: $407,400 |
- | - | - | - | $83,427 | - | - | - |
- - kWh |
- - kW-months/year |
$83,427 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $25,167 Cost: $70,338 |
$15,961 | 301,142 | $9,206 | 1,158 | - | - | - | - |
$15,961 301,142 kWh |
$9,206 1,158 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,923 Cost: $2,911 |
$3,923 | 74,013 | - | - | - | - | - | - |
$3,923 74,013 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,152 Cost: $4,457 |
- | - | - | - | - | - | $2,152 | 794 |
- - kWh |
- - kW-months/year |
- - $ |
$2,152 794 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $114,669 Cost: $485,106 |
$19,884 | 375,155 | $9,206 | 1,158 | $83,427 | - | $2,152 | 794 | $19,884 375,155 kWh |
$9,206 1,158 kW-months/year |
$83,427 - $ |
$2,152 794 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,075 Cost: $7,368 |
$3,923 | 74,013 | - | - | - | - | $2,152 | 794 | $3,923 74,013 kWh |
- - kW-months/year |
- - $ |
$2,152 794 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas |