IAC Assessment: OK1040
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK1040
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2021
Principal Product Architectural fencing
NAICS 332323 - Ornamental and Architectural Metal Work Manufacturing
SIC 3446 - Architectural Metal Work
Sales $100,000,000-$500,000,000
# of Employees 523
Plant Area (Sq.Ft.) 696,530
Annual Production 60,000 Tons
Production Hrs. Annual 2,340
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $994,163 18,757,788 kWh $0.05
Electricity Demand $464,296 58,402 kW-months/year $7.95
Natural Gas $464,451 171,384 MMBtu $2.71
TOTAL ENERGY COSTS $1,922,910
RECOMMENDED SAVINGS* $114,669 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,075
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$83,427
Cost:
$407,400
- - - - $83,427 - - - -
-
kWh
-
-
kW-months/year
$83,427
-
$
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$25,167
Cost:
$70,338
$15,961 301,142 $9,206 1,158 - - - - $15,961
301,142
kWh
$9,206
1,158
kW-months/year
-
-
$
-
-
MMBtu
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,923
Cost:
$2,911
$3,923 74,013 - - - - - - $3,923
74,013
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,152
Cost:
$4,457
- - - - - - $2,152 794 -
-
kWh
-
-
kW-months/year
-
-
$
$2,152
794
MMBtu
TOTAL RECOMMENDED Savings:
$114,669
Cost:
$485,106
$19,884 375,155 $9,206 1,158 $83,427 - $2,152 794 $19,884
375,155
kWh
$9,206
1,158
kW-months/year
$83,427
-
$
$2,152
794
MMBtu
TOTAL IMPLEMENTED Savings:
$6,075
Cost:
$7,368
$3,923 74,013 - - - - $2,152 794 $3,923
74,013
kWh
-
-
kW-months/year
-
-
$
$2,152
794
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas