Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2022 |
Principal Product | Gas turbines |
NAICS | 333611 - Turbine and Turbine Generator Set Units Manufacturing |
SIC | 3511 - Turbines And Turbine Generator Sets |
Sales | $50,000,000-$100,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 110,000 |
Annual Production | 2,500 Units |
Production Hrs. Annual | 6,600 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $242,866 | 4,047,774 | kWh | $0.06 |
Natural Gas | $10,874 | 2,025 | MMBtu | $5.37 |
LPG | $8,465 | 215 | MMBtu | $39.37 |
TOTAL ENERGY COSTS | $263,765 | |||
RECOMMENDED SAVINGS* | $26,721 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,002 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,809 Cost: $9,600 |
- | - | $2,809 | - | - | - | - | - |
- - kWh |
$2,809 - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,329 Cost: - |
$1,329 | 22,156 | - | - | - | - | - | - |
$1,329 22,156 kWh |
- - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,014 Cost: $990 |
$4,014 | 66,903 | - | - | - | - | - | - |
$4,014 66,903 kWh |
- - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $3,689 Cost: $3,294 |
- | - | - | - | $3,689 | 687 | - | - |
- - kWh |
- - $ |
$3,689 687 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $2,659 Cost: $8,954 |
$2,659 | 44,312 | - | - | - | - | - | - |
$2,659 44,312 kWh |
- - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,927 Cost: $3,985 |
$2,927 | 48,788 | - | - | - | - | - | - |
$2,927 48,788 kWh |
- - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,761 Cost: $4,884 |
$6,761 | 112,684 | - | - | - | - | - | - |
$6,761 112,684 kWh |
- - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $2,533 Cost: $440 |
- | - | - | - | - | - | $2,533 | - |
- - kWh |
- - $ |
- - MMBtu |
$2,533 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,721 Cost: $32,147 |
$17,690 | 294,843 | $2,809 | - | $3,689 | 687 | $2,533 | - | $17,690 294,843 kWh |
$2,809 - $ |
$3,689 687 MMBtu |
$2,533 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,002 Cost: $9,944 |
$8,002 | 133,371 | - | - | - | - | - | - | $8,002 133,371 kWh |
- - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost |