IAC Assessment: OK1143
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2025
Principal Product Tilling & harvesting equipment
NAICS 333111 - Farm Machinery and Equipment Manufacturing
SIC 3523 - Farm Machinery And Equipment
Sales $5,000,000-$10,000,000
# of Employees 40
Plant Area (Sq.Ft.) 110,000
Annual Production 875,000 Pounds
Production Hrs. Annual 2,600
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $34,101 387,648 kWh $0.09
Electricity Demand $4,689 647 kW-months/year $7.25
Natural Gas $16,823 3,055 MMBtu $5.51
TOTAL ENERGY COSTS $55,613
RECOMMENDED SAVINGS* $10,088 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$693
Cost:
$3,315
$502 5,702 $191 26 - - - - $502
5,702
kWh
$191
26
kW-months/year
-
-
MMBtu
-
-
$
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$3,424
Cost:
$25,650
$3,424 38,910 - - - - - - $3,424
38,910
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,973
Cost:
$1,950
- - - - $1,973 358 - - -
-
kWh
-
-
kW-months/year
$1,973
358
MMBtu
-
-
$
04: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$609
Cost:
$4,675
$609 6,923 - - - - - - $609
6,923
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,910
Cost:
$4,426
$1,910 21,699 - - - - - - $1,910
21,699
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
06: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,479
Cost:
$2,457
- - - - - - $1,479 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,479
-
$
TOTAL RECOMMENDED Savings:
$10,088
Cost:
$42,473
$6,445 73,234 $191 26 $1,973 358 $1,479 - $6,445
73,234
kWh
$191
26
kW-months/year
$1,973
358
MMBtu
$1,479
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes