IAC Assessment: OR0008
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0008
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1987
Principal Product LUMBER
NAICS n/a
SIC 2426 - Hardwood Dimension & Flooring Mills
Sales $5,000,000-$10,000,000
# of Employees 60
Plant Area (Sq.Ft.) 0
Annual Production 12,000 Thousand Feet
Production Hrs. Annual 8,736
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $53,393 1,029,308 kWh $0.05
Wood $65,700 150,672 MMBtu $0.44
TOTAL ENERGY COSTS $119,093
RECOMMENDED SAVINGS* $17,708 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $5,442
#|Description Savings
Cost
Status Electricity Usage Wood Electricity Usage Wood
$ kWh $ MMBtu
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$551
Cost:
-
$551 10,551 - - $551
10,551
kWh
-
-
MMBtu
02: 2.6232 INSTALL SET-BACK TIMERS Savings:
$2,187
Cost:
$100
$2,187 41,911 - - $2,187
41,911
kWh
-
-
MMBtu
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$729
Cost:
$80
$729 14,068 - - $729
14,068
kWh
-
-
MMBtu
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$334
Cost:
$100
$334 6,448 - - $334
6,448
kWh
-
-
MMBtu
05: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$1,408
Cost:
$705
- - $1,408 3,285 -
-
kWh
$1,408
3,285
MMBtu
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,949
Cost:
$1,000
$1,949 37,515 - - $1,949
37,515
kWh
-
-
MMBtu
07: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$882
Cost:
$609
- - $882 2,059 -
-
kWh
$882
2,059
MMBtu
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$159
Cost:
$128
$159 2,931 - - $159
2,931
kWh
-
-
MMBtu
09: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$6,901
Cost:
$6,627
$6,901 150,059 - - $6,901
150,059
kWh
-
-
MMBtu
10: 2.2511 INSULATE BARE EQUIPMENT Savings:
$2,608
Cost:
$2,691
- - $2,608 6,085 -
-
kWh
$2,608
6,085
MMBtu
TOTAL RECOMMENDED Savings:
$17,708
Cost:
$12,040
$12,810 263,483 $4,898 11,429 $12,810
263,483
kWh
$4,898
11,429
MMBtu
TOTAL IMPLEMENTED Savings:
$5,442
Cost:
$3,791
$2,834 54,514 $2,608 6,085 $2,834
54,514
kWh
$2,608
6,085
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Wood Electricity Usage Wood