Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1989 |
Principal Product | FROZEN PRODUCE |
NAICS | n/a |
SIC | 2037 - Frozen Fruits And Vegetables |
Sales | $50,000,000-$100,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 31,100 Tons |
Production Hrs. Annual | 5,712 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $653,414 | 14,995,897 | kWh | $0.04 |
Natural Gas | $76,954 | 18,978 | MMBtu | $4.05 |
TOTAL ENERGY COSTS | $730,368 | |||
RECOMMENDED SAVINGS* | $26,853 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $26,309 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $8,348 Cost: - |
$8,348 | 189,625 | - | - | - | - |
$8,348 189,625 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $5,777 Cost: - |
$5,777 | 131,301 | - | - | - | - |
$5,777 131,301 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $3,193 Cost: - |
$3,193 | 72,685 | - | - | - | - |
$3,193 72,685 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $3,718 Cost: - |
$3,041 | 69,168 | - | - | $677 | - |
$3,041 69,168 kWh |
- - MMBtu |
$677 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,679 Cost: $500 |
- | - | $1,679 | 415 | - | - |
- - kWh |
$1,679 415 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $544 Cost: $650 |
- | - | $544 | 134 | - | - |
- - kWh |
$544 134 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2123 INSULATE FEEDWATER TANK |
Savings: $435 Cost: $658 |
- | - | $435 | 107 | - | - |
- - kWh |
$435 107 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $3,159 Cost: $6,810 |
$3,159 | - | - | - | - | - |
$3,159 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,853 Cost: $8,618 |
$23,518 | 462,779 | $2,658 | 656 | $677 | - | $23,518 462,779 kWh |
$2,658 656 MMBtu |
$677 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $26,309 Cost: $7,968 |
$23,518 | 462,779 | $2,114 | 522 | $677 | - | $23,518 462,779 kWh |
$2,114 522 MMBtu |
$677 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |