Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1989 |
Principal Product | MARGARINE AND SHORTENING |
NAICS | n/a |
SIC | 2035 - Pickles, Sauces, And Salad Dressings |
Sales | $5,000,000-$10,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 60,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $237,428 | 5,385,698 | kWh | $0.04 |
Natural Gas | $116,983 | 25,786 | MMBtu | $4.54 |
TOTAL ENERGY COSTS | $354,411 | |||
RECOMMENDED SAVINGS* | $49,654 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $42,660 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $14,990 Cost: - |
$11,889 | 270,223 | - | - | $3,101 | - |
$11,889 270,223 kWh |
- - MMBtu |
$3,101 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $2,926 Cost: - |
$2,926 | 66,530 | - | - | - | - |
$2,926 66,530 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE |
Savings: $458 Cost: - |
- | - | $458 | 101 | - | - |
- - kWh |
$458 101 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2111 INSTALL STEAM TRAP |
Savings: $23,375 Cost: $2,335 |
- | - | $23,100 | 5,088 | $275 | - |
- - kWh |
$23,100 5,088 MMBtu |
$275 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $444 Cost: $500 |
- | - | $444 | 123 | - | - |
- - kWh |
$444 123 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $467 Cost: $503 |
$467 | 10,551 | - | - | - | - |
$467 10,551 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $4,450 Cost: $8,000 |
$4,450 | - | - | - | - | - |
$4,450 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,544 Cost: $5,400 |
$2,544 | - | - | - | - | - |
$2,544 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $49,654 Cost: $16,738 |
$22,276 | 347,304 | $24,002 | 5,312 | $3,376 | - | $22,276 347,304 kWh |
$24,002 5,312 MMBtu |
$3,376 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $42,660 Cost: $3,338 |
$15,282 | 347,304 | $24,002 | 5,312 | $3,376 | - | $15,282 347,304 kWh |
$24,002 5,312 MMBtu |
$3,376 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |