IAC Assessment: OR0102
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1990
Principal Product DOOR FRAMES
NAICS n/a
SIC 2431 - Millwork
Sales $5,000,000-$10,000,000
# of Employees 70
Plant Area (Sq.Ft.) 0
Annual Production 5,000 Thousand Feet
Production Hrs. Annual 4,510
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $100,031 2,420,574 kWh $0.04
TOTAL ENERGY COSTS $100,031
RECOMMENDED SAVINGS* $3,311 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $925
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$925
Cost:
$1,950
$925 - $925
-
kWh
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$257
Cost:
$595
$257 6,448 $257
6,448
kWh
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,129
Cost:
$6,255
$2,129 52,169 $2,129
52,169
kWh
TOTAL RECOMMENDED Savings:
$3,311
Cost:
$8,800
$3,311 58,617 $3,311
58,617
kWh
TOTAL IMPLEMENTED Savings:
$925
Cost:
$1,950
$925 - $925
-
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage