IAC logo
IAC Assessment: OR0165
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0165
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1992
Principal Product Frozen Yorurt
NAICS n/a
SIC 2023 - Dry, Condensed, Evaporated Products
Sales $10,000,000-$50,000,000
# of Employees 34
Plant Area (Sq.Ft.) 0
Annual Production 10,700,000 Pounds
Production Hrs. Annual 3,965
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $85,612 2,298,359 kWh $0.04
Natural Gas $14,778 3,768 MMBtu $3.92
TOTAL ENERGY COSTS $100,390
RECOMMENDED SAVINGS* $9,413 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,057
#|Description Savings
Cost
Status Electricity Usage LPG Administrative Changes Electricity Usage LPG Administrative Changes
$ kWh $ MMBtu $ $
01: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS Savings:
$4,045
Cost:
$500
$4,045 121,630 - - - - $4,045
121,630
kWh
-
-
MMBtu
-
-
$
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,788
Cost:
-
- - $1,788 498 - - -
-
kWh
$1,788
498
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,356
Cost:
-
$850 22,860 - - $506 - $850
22,860
kWh
-
-
MMBtu
$506
-
$
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,074
Cost:
$2,250
$1,074 - - - - - $1,074
-
kWh
-
-
MMBtu
-
-
$
05: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS Savings:
$830
Cost:
-
$830 24,912 - - - - $830
24,912
kWh
-
-
MMBtu
-
-
$
06: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT Savings:
$320
Cost:
$824
$320 8,499 - - - - $320
8,499
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$9,413
Cost:
$3,574
$7,119 177,901 $1,788 498 $506 - $7,119
177,901
kWh
$1,788
498
MMBtu
$506
-
$
TOTAL IMPLEMENTED Savings:
$8,057
Cost:
$3,574
$6,269 155,041 $1,788 498 - - $6,269
155,041
kWh
$1,788
498
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage LPG Administrative Changes Electricity Usage LPG Administrative Changes