IAC Assessment: OR0187
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0187
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1993
Principal Product Dimensional Lumber
NAICS n/a
SIC 2421 - Sawmills And Planing Mills, General
Sales $50,000,000-$100,000,000
# of Employees 110
Plant Area (Sq.Ft.) 0
Annual Production 67,000 Thousand Feet
Production Hrs. Annual 8,736
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $526,062 12,853,459 kWh $0.04
Natural Gas $375,672 101,883 MMBtu $3.69
TOTAL ENERGY COSTS $901,734
RECOMMENDED SAVINGS* $155,672 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $48,735
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Electricity Usage Natural Gas Personnel Changes
$ kWh $ MMBtu $ $
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$10,305
Cost:
$1,800
$10,305 314,478 - - - - $10,305
314,478
kWh
-
-
MMBtu
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,623
Cost:
$5,500
$5,623 146,249 - - - - $5,623
146,249
kWh
-
-
MMBtu
-
-
$
03: 2.3412 USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR Savings:
$75,830
Cost:
$146,156
$51,348 1,566,530 $24,482 - - - $51,348
1,566,530
kWh
$24,482
-
MMBtu
-
-
$
04: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,468
Cost:
$1,287
- - $1,468 398 - - -
-
kWh
$1,468
398
MMBtu
-
-
$
05: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$29,864
Cost:
$32,720
$29,864 910,903 - - - - $29,864
910,903
kWh
-
-
MMBtu
-
-
$
06: 2.7134 USE PHOTOCELL CONTROLS Savings:
$12,486
Cost:
$4,100
$10,279 251,172 - - $2,207 - $10,279
251,172
kWh
-
-
MMBtu
$2,207
-
$
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,372
Cost:
-
$2,372 54,220 - - - - $2,372
54,220
kWh
-
-
MMBtu
-
-
$
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,243
Cost:
$3,171
$1,243 31,653 - - - - $1,243
31,653
kWh
-
-
MMBtu
-
-
$
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,921
Cost:
$9,700
$2,921 75,615 - - - - $2,921
75,615
kWh
-
-
MMBtu
-
-
$
10: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$13,560
Cost:
$28,500
$13,560 - - - - - $13,560
-
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$155,672
Cost:
$232,934
$127,515 3,350,820 $25,950 398 $2,207 - $127,515
3,350,820
kWh
$25,950
398
MMBtu
$2,207
-
$
TOTAL IMPLEMENTED Savings:
$48,735
Cost:
$50,887
$45,060 841,734 $1,468 398 $2,207 - $45,060
841,734
kWh
$1,468
398
MMBtu
$2,207
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Personnel Changes Electricity Usage Natural Gas Personnel Changes