Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1996 |
Principal Product | Formed Sheet Metal |
NAICS | n/a |
SIC | 3442 - Metal Doors, Sash, And Trim |
Sales | $10,000,000-$50,000,000 |
# of Employees | 170 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 1,500,000 Pieces |
Production Hrs. Annual | 7,200 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $52,647 | 1,415,006 | kWh | $0.04 |
Electricity Demand | $12,058 | 2,868 | kW-months/year | $4.20 |
Electricity Fees | $576 | - | $ | - |
Natural Gas | $19,315 | 4,566 | MMBtu | $4.23 |
TOTAL ENERGY COSTS | $143,209 | |||
RECOMMENDED SAVINGS* | $25,844 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,943 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6125 KEEP EQUIPMENT CLEAN |
Savings: $2,162 Cost: - |
- | - | - | - | $2,282 | 600 | - | - | $(-120) | - |
- - kWh |
- - kW-months/year |
$2,282 600 MMBtu |
- - Tgal |
$(-120) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,493 Cost: $1,000 |
$1,222 | 33,705 | $271 | 62 | - | - | - | - | - | - |
$1,222 33,705 kWh |
$271 62 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,288 Cost: $2,371 |
$1,012 | 28,136 | $276 | 58 | - | - | - | - | - | - |
$1,012 28,136 kWh |
$276 58 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6112 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME |
Savings: $20,901 Cost: $62,500 |
$(-91) | (-2,638) | - | - | $(-500) | (-132) | $19,532 | 7,092 | $1,960 | - |
$(-91) (-2,638) kWh |
- - kW-months/year |
$(-500) (-132) MMBtu |
$19,532 7,092 Tgal |
$1,960 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,844 Cost: $65,871 |
$2,143 | 59,203 | $547 | 120 | $1,782 | 468 | $19,532 | 7,092 | $1,840 | - | $2,143 59,203 kWh |
$547 120 kW-months/year |
$1,782 468 MMBtu |
$19,532 7,092 Tgal |
$1,840 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,943 Cost: $3,371 |
$2,234 | 61,841 | $547 | 120 | $2,282 | 600 | - | - | $(-120) | - | $2,234 61,841 kWh |
$547 120 kW-months/year |
$2,282 600 MMBtu |
- - Tgal |
$(-120) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes |