IAC Assessment: OR0279
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1996
Principal Product Popsicles, Frozen Fruit Bars
NAICS n/a
SIC 2024 - Ice Cream And Frozen Desserts
Sales $1,000,000-$5,000,000
# of Employees 65
Plant Area (Sq.Ft.) 85,360
Annual Production 33,000,000 Pieces
Production Hrs. Annual 6,300
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $30,064 1,355,803 kWh $0.02
Electricity Demand $13,326 3,756 kW-months/year $3.55
Electricity Fees $4,525 - $ -
Natural Gas $14,630 3,272 MMBtu $4.47
TOTAL ENERGY COSTS $85,275
RECOMMENDED SAVINGS* $8,904 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $7,707
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Water Consumption Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Water Consumption
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ Tgal
01: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$1,604
Cost:
-
$1,604 71,219 - - - - - - - - - - $1,604
71,219
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
Tgal
02: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$661
Cost:
-
- - - - - - - - $661 2,400 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$661
2,400
lb
-
-
Tgal
03: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES Savings:
$4,754
Cost:
$750
- - - - - - $3,260 1,451,520 - - $1,494 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,260
1,451,520
Tgal
-
-
lb
$1,494
-
Tgal
04: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER Savings:
$272
Cost:
$242
- - - - $272 73 - - - - - - -
-
kWh
-
-
kW-months/year
$272
73
MMBtu
-
-
Tgal
-
-
lb
-
-
Tgal
05: 2.1232 KEEP BOILER TUBES CLEAN Savings:
$1,349
Cost:
$1,500
- - - - $1,349 362 - - - - - - -
-
kWh
-
-
kW-months/year
$1,349
362
MMBtu
-
-
Tgal
-
-
lb
-
-
Tgal
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$264
Cost:
$738
$176 7,913 $88 23 - - - - - - - - $176
7,913
kWh
$88
23
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
lb
-
-
Tgal
TOTAL RECOMMENDED Savings:
$8,904
Cost:
$3,230
$1,780 79,132 $88 23 $1,621 435 $3,260 1,451,520 $661 2,400 $1,494 - $1,780
79,132
kWh
$88
23
kW-months/year
$1,621
435
MMBtu
$3,260
1,451,520
Tgal
$661
2,400
lb
$1,494
-
Tgal
TOTAL IMPLEMENTED Savings:
$7,707
Cost:
$2,250
$1,604 71,219 - - $1,349 362 $3,260 1,451,520 - - $1,494 - $1,604
71,219
kWh
-
-
kW-months/year
$1,349
362
MMBtu
$3,260
1,451,520
Tgal
-
-
lb
$1,494
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ lb $ Tgal
Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Water Consumption Electricity Usage Electricity Demand Natural Gas Water Disposal Solid Waste (non-haz) Water Consumption