Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1997 |
Principal Product | Manufactured Homes |
NAICS | n/a |
SIC | 2452 - Prefabricated Wood Buildings |
Sales | $50,000,000-$100,000,000 |
# of Employees | 458 |
Plant Area (Sq.Ft.) | 240,000 |
Annual Production | 2,854 Pieces |
Production Hrs. Annual | 5,145 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $82,999 | 2,783,705 | kWh | $0.03 |
Electricity Demand | $2,778 | 609 | kW-months/year | $4.56 |
Electricity Fees | $168 | - | $ | - |
Natural Gas | $63,782 | 13,296 | MMBtu | $4.80 |
TOTAL ENERGY COSTS | $679,077 | |||
RECOMMENDED SAVINGS* | $61,990 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,250 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.1172 REVISE RAW MATERIAL SPECS |
Savings: $32,300 Cost: $104,000 |
- | - | - | - | - | - | - | - | $32,300 | 2,291,000 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$32,300 2,291,000 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.1175 USE A DIFFERENT OR RECYCLED RAW MATERIAL |
Savings: $17,270 Cost: - |
- | - | - | - | - | - | - | - | $2,570 | 182,400 | $14,700 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$2,570 182,400 lb |
$14,700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $480 Cost: - |
- | - | - | - | - | - | $480 | 45 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$480 45 gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $260 Cost: - |
- | - | - | - | - | - | - | - | $260 | 18,600 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$260 18,600 lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,770 Cost: $2,885 |
$1,260 | 46,600 | $510 | 109 | - | - | - | - | - | - | - | - |
$1,260 46,600 kWh |
$510 109 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: - Cost: $2,000 |
- | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $450 Cost: $2,000 |
$320 | 12,016 | $130 | 28 | - | - | - | - | - | - | - | - |
$320 12,016 kWh |
$130 28 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR |
Savings: $9,460 Cost: $134,000 |
$3,350 | 123,974 | $1,340 | 289 | $4,770 | 994 | - | - | - | - | - | - |
$3,350 123,974 kWh |
$1,340 289 kW-months/year |
$4,770 994 MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $61,990 Cost: $244,885 |
$4,930 | 182,590 | $1,980 | 426 | $4,770 | 994 | $480 | 45 | $35,130 | 2,492,000 | $14,700 | - | $4,930 182,590 kWh |
$1,980 426 kW-months/year |
$4,770 994 MMBtu |
$480 45 gal |
$35,130 2,492,000 lb |
$14,700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,250 Cost: $4,885 |
$1,260 | 46,600 | $510 | 109 | - | - | $480 | 45 | - | - | - | - | $1,260 46,600 kWh |
$510 109 kW-months/year |
- - MMBtu |
$480 45 gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Personnel Changes |