IAC logo
IAC Assessment: OR0290
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0290
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1997
Principal Product Asphalt
NAICS n/a
SIC 2951 - Asphalt Paving Mixtures And Blocks
Sales $1,000,000-$5,000,000
# of Employees 3
Plant Area (Sq.Ft.) 0
Annual Production 163,500 Tons
Production Hrs. Annual 2,000
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $15,505 635,111 kWh $0.02
Electricity Demand $24,602 5,592 kW-months/year $4.40
Electricity Fees $3,177 - $ -
LPG $271,250 35,456 MMBtu $7.65
Fuel Oil #2 $2,520 469 MMBtu $5.37
TOTAL ENERGY COSTS $344,054
RECOMMENDED SAVINGS* $38,449 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $349
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #2 Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Fuel Oil #2 Solid Waste (non-haz) Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ lb $ $
01: 4.4230 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$7,230
Cost:
$20,000
$(-870) (-40,445) $(-2,380) (-486) $2,510 469 - - $7,970 - $(-870)
(-40,445)
kWh
$(-2,380)
(-486)
kW-months/year
$2,510
469
MMBtu
-
-
lb
$7,970
-
$
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$3,870
Cost:
$5,000
$8,460 394,197 $4,410 900 $(-9,000) (-1,680) - - - - $8,460
394,197
kWh
$4,410
900
kW-months/year
$(-9,000)
(-1,680)
MMBtu
-
-
lb
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$349
Cost:
$2,216
$61 2,931 $288 59 - - - - - - $61
2,931
kWh
$288
59
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
04: 3.5311 RECOVER AND REUSE WASTE MATERIAL Savings:
$27,000
Cost:
$260,000
- - - - - - $27,000 2,460,000 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$27,000
2,460,000
lb
-
-
$
TOTAL RECOMMENDED Savings:
$38,449
Cost:
$287,216
$7,651 356,683 $2,318 473 $(-6,490) (-1,211) $27,000 2,460,000 $7,970 - $7,651
356,683
kWh
$2,318
473
kW-months/year
$(-6,490)
(-1,211)
MMBtu
$27,000
2,460,000
lb
$7,970
-
$
TOTAL IMPLEMENTED Savings:
$349
Cost:
$2,216
$61 2,931 $288 59 - - - - - - $61
2,931
kWh
$288
59
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $
Electricity Usage Electricity Demand Fuel Oil #2 Solid Waste (non-haz) Personnel Changes Electricity Usage Electricity Demand Fuel Oil #2 Solid Waste (non-haz) Personnel Changes