IAC logo
IAC Assessment: OR0297
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0297
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1997
Principal Product Steamed Rice
NAICS n/a
SIC 2044 - Rice Milling
Sales $10,000,000-$50,000,000
# of Employees 12
Plant Area (Sq.Ft.) 0
Annual Production 18,900,000 Pounds
Production Hrs. Annual 2,626
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $39,339 1,114,596 kWh $0.04
Electricity Demand $9,504 2,340 kW-months/year $4.06
Electricity Fees $126 - $ -
Natural Gas $20,021 4,335 MMBtu $4.62
TOTAL ENERGY COSTS $82,811
RECOMMENDED SAVINGS* $12,108 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $ $ $
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$3,530
Cost:
-
$3,530 105,803 - - - - - - - - - - $3,530
105,803
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$2,121
Cost:
$3,853
$1,643 48,359 $478 96 - - - - - - - - $1,643
48,359
kWh
$478
96
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,160
Cost:
$500
- - - - $1,160 252 - - - - - - -
-
kWh
-
-
kW-months/year
$1,160
252
MMBtu
-
-
Tgal
-
-
$
-
-
$
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$171
Cost:
-
$133 3,810 - - - - - - $17 - $21 - $133
3,810
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$17
-
$
$21
-
$
05: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$2,706
Cost:
$8,250
- - - - - - $2,706 1,775,000 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$2,706
1,775,000
Tgal
-
-
$
-
-
$
06: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$2,420
Cost:
$130
- - - - $2,350 510 $70 54,000 - - - - -
-
kWh
-
-
kW-months/year
$2,350
510
MMBtu
$70
54,000
Tgal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$12,108
Cost:
$12,733
$5,306 157,972 $478 96 $3,510 762 $2,776 1,829,000 $17 - $21 - $5,306
157,972
kWh
$478
96
kW-months/year
$3,510
762
MMBtu
$2,776
1,829,000
Tgal
$17
-
$
$21
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Ancillary Material Cost