Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1998 |
Principal Product | Investment Castings |
NAICS | n/a |
SIC | 3724 - Aircraft Engines And Engine Parts |
Sales | $50,000,000-$100,000,000 |
# of Employees | 600 |
Plant Area (Sq.Ft.) | 203,696 |
Annual Production | 3,172,304 Pounds |
Production Hrs. Annual | 8,760 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $545,564 | 31,300,704 | kWh | $0.02 |
Electricity Demand | $376,763 | 661,956 | kW-months/year | $0.57 |
Electricity Fees | $9,453 | - | $ | - |
Natural Gas | $476,523 | 144,972 | MMBtu | $3.29 |
TOTAL ENERGY COSTS | $1,967,703 | |||
RECOMMENDED SAVINGS* | $246,504 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $194,253 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Solid Waste (haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Solid Waste (haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | lb | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $20,329 Cost: $15,000 |
$12,006 | 688,159 | $8,323 | 1,218 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$12,006 688,159 kWh |
$8,323 1,218 kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $33,509 Cost: $5,600 |
$19,764 | 1,133,060 | $13,745 | 2,012 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$19,764 1,133,060 kWh |
$13,745 2,012 kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $16,330 Cost: $15,000 |
- | - | - | - | - | - | $8,935 | 70,200 | $6,695 | 183,400 | - | - | - | - | - | - | - | - | $700 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$8,935 70,200 lb |
$6,695 183,400 lb |
- - $ |
- - $ |
- - $ |
- - $ |
$700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7131 ADD AREA LIGHTING SWITCHES |
Savings: $3,712 Cost: $2,800 |
$3,712 | 213,072 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$3,712 213,072 kWh |
- - kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: - Cost: $57,200 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $48,539 Cost: $3,154 |
$(-600) | (-31,360) | $(-98) | (-14) | $49,237 | 12,614,400 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$(-600) (-31,360) kWh |
$(-98) (-14) kW-months/year |
$49,237 12,614,400 Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $89,264 Cost: $5,400 |
- | - | - | - | - | - | - | - | - | - | $(-1,536) | - | - | - | $82,800 | - | $8,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - lb |
- - lb |
$(-1,536) - $ |
- - $ |
$82,800 - $ |
$8,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $3,267 Cost: $5,409 |
$1,847 | 106,096 | $1,420 | 208 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$1,847 106,096 kWh |
$1,420 208 kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $4,032 Cost: $980 |
$3,647 | 209,261 | $385 | 56 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$3,647 209,261 kWh |
$385 56 kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $27,522 Cost: $71,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $27,522 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - lb |
- - lb |
- - $ |
$27,522 - $ |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $246,504 Cost: $181,543 |
$40,376 | 2,318,288 | $23,775 | 3,480 | $49,237 | 12,614,400 | $8,935 | 70,200 | $6,695 | 183,400 | $(-1,536) | - | $27,522 | - | $82,800 | - | $8,000 | - | $700 | - | $40,376 2,318,288 kWh |
$23,775 3,480 kW-months/year |
$49,237 12,614,400 Tgal |
$8,935 70,200 lb |
$6,695 183,400 lb |
$(-1,536) - $ |
$27,522 - $ |
$82,800 - $ |
$8,000 - $ |
$700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $194,253 Cost: $118,389 |
$37,264 | 2,136,576 | $23,873 | 3,494 | - | - | $8,935 | 70,200 | $6,695 | 183,400 | $(-1,536) | - | $27,522 | - | $82,800 | - | $8,000 | - | $700 | - | $37,264 2,136,576 kWh |
$23,873 3,494 kW-months/year |
- - Tgal |
$8,935 70,200 lb |
$6,695 183,400 lb |
$(-1,536) - $ |
$27,522 - $ |
$82,800 - $ |
$8,000 - $ |
$700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | lb | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Solid Waste (haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production | Electricity Usage | Electricity Demand | Water Disposal | Solid Waste (non-haz) | Solid Waste (haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | By-product Production |