IAC Assessment: OR0397
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0397
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2001
Principal Product Steel Castings
NAICS n/a
SIC 3325 - Steel Foundries, Nec
Sales $5,000,000-$10,000,000
# of Employees 85
Plant Area (Sq.Ft.) 75,000
Annual Production 2,500,000 Pounds
Production Hrs. Annual 6,240
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $148,538 7,188,140 kWh $0.02
Electricity Demand $87,685 27,192 kW-months/year $3.22
Electricity Fees $20,968 - $ -
Natural Gas $292,059 38,366 MMBtu $7.61
TOTAL ENERGY COSTS $549,250
RECOMMENDED SAVINGS* $26,355 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,329
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Electricity Usage Electricity Demand Electricity Fees
$ kWh $ kW-months/year $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$5,700
Cost:
$5,500
$4,600 171,300 $1,100 329 - - $4,600
171,300
kWh
$1,100
329
kW-months/year
-
-
$
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$9,700
Cost:
$18,800
$7,000 260,800 $2,700 821 - - $7,000
260,800
kWh
$2,700
821
kW-months/year
-
-
$
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$6,600
Cost:
$15,463
$5,300 197,541 $1,300 408 - - $5,300
197,541
kWh
$1,300
408
kW-months/year
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,929
Cost:
$1,568
$1,516 56,599 $413 127 - - $1,516
56,599
kWh
$413
127
kW-months/year
-
-
$
05: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$2,426
Cost:
$4,000
- - - - $2,426 - -
-
kWh
-
-
kW-months/year
$2,426
-
$
TOTAL RECOMMENDED Savings:
$26,355
Cost:
$45,331
$18,416 686,240 $5,513 1,685 $2,426 - $18,416
686,240
kWh
$5,513
1,685
kW-months/year
$2,426
-
$
TOTAL IMPLEMENTED Savings:
$17,329
Cost:
$25,868
$13,116 488,699 $4,213 1,277 - - $13,116
488,699
kWh
$4,213
1,277
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Electricity Fees Electricity Usage Electricity Demand Electricity Fees