IAC logo
IAC Assessment: OR0402
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0402
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2001
Principal Product horse/livestock and car trailers
NAICS n/a
SIC 3799 - Transportation Equipment, Nec
Sales $5,000,000-$10,000,000
# of Employees 80
Plant Area (Sq.Ft.) 70,000
Annual Production 399 Pieces
Production Hrs. Annual 2,040
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $17,727 414,370 kWh $0.04
Electricity Demand $2,563 1,368 kW-months/year $1.87
Electricity Fees $3,023 - $ -
TOTAL ENERGY COSTS $23,313
RECOMMENDED SAVINGS* $62,384 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $59,880
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $ $ $
01: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$53,000
Cost:
$45,000
- - - - - - $53,000 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$53,000
-
$
-
-
$
02: 4.4310 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$6,880
Cost:
$1,230
- - - - - - $6,880 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$6,880
-
$
-
-
$
03: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,310
Cost:
$1,100
- - - - $1,310 - - - - - -
-
kWh
-
-
kW-months/year
$1,310
-
$
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,194
Cost:
$3,600
$552 12,896 $464 74 - - $(-12) - $190 - $552
12,896
kWh
$464
74
kW-months/year
-
-
$
$(-12)
-
$
$190
-
$
TOTAL RECOMMENDED Savings:
$62,384
Cost:
$50,930
$552 12,896 $464 74 $1,310 - $59,868 - $190 - $552
12,896
kWh
$464
74
kW-months/year
$1,310
-
$
$59,868
-
$
$190
-
$
TOTAL IMPLEMENTED Savings:
$59,880
Cost:
$46,230
- - - - - - $59,880 - - - -
-
kWh
-
-
kW-months/year
-
-
$
$59,880
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Electricity Fees Personnel Changes Ancillary Material Cost