Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2003 |
Principal Product | Dimensional Lumber |
NAICS | n/a |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | n/a |
# of Employees | 0 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Thousand Feet |
Production Hrs. Annual | 2,448 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $183,229 | 3,326,600 | kWh | $0.06 |
Electricity Demand | $38,029 | 13,447 | kW-months/year | $2.83 |
Electricity Fees | $3,149 | - | $ | - |
LPG | $88,200 | 8,070 | MMBtu | $10.93 |
TOTAL ENERGY COSTS | $312,607 | |||
RECOMMENDED SAVINGS* | $48,570 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $31,860 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $7,000 Cost: $580 |
$5,600 | 102,000 | $1,400 | 498 | - | - | - | - | - | - |
$5,600 102,000 kWh |
$1,400 498 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $3,700 Cost: $2,000 |
$3,700 | 66,000 | - | - | - | - | - | - | - | - |
$3,700 66,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $11,950 Cost: $880 |
$9,200 | 166,000 | - | - | - | - | - | - | $2,750 | - |
$9,200 166,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$2,750 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $3,000 Cost: $150 |
- | - | - | - | $3,300 | 300 | $(-300) | - | - | - |
- - kWh |
- - kW-months/year |
$3,300 300 MMBtu |
$(-300) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $9,910 Cost: $14,200 |
$9,910 | 180,000 | - | - | - | - | - | - | - | - |
$9,910 180,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $12,200 Cost: $24,350 |
$9,150 | 164,450 | $3,050 | 1,110 | - | - | - | - | - | - |
$9,150 164,450 kWh |
$3,050 1,110 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $810 Cost: - |
$630 | 11,300 | $180 | 64 | - | - | - | - | - | - |
$630 11,300 kWh |
$180 64 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,570 Cost: $42,160 |
$38,190 | 689,750 | $4,630 | 1,672 | $3,300 | 300 | $(-300) | - | $2,750 | - | $38,190 689,750 kWh |
$4,630 1,672 kW-months/year |
$3,300 300 MMBtu |
$(-300) - $ |
$2,750 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $31,860 Cost: $15,810 |
$24,710 | 448,000 | $1,400 | 498 | $3,300 | 300 | $(-300) | - | $2,750 | - | $24,710 448,000 kWh |
$1,400 498 kW-months/year |
$3,300 300 MMBtu |
$(-300) - $ |
$2,750 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes |