IAC Assessment: OR0449
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0449
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2004
Principal Product Manufactured Homes
NAICS 321992 - Prefabricated Wood Building Manufacturing
SIC 2452 - Prefabricated Wood Buildings
Sales $10,000,000-$50,000,000
# of Employees 155
Plant Area (Sq.Ft.) 120,000
Annual Production 1,018 Pieces
Production Hrs. Annual 2,000
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $56,953 952,270 kWh $0.06
Electricity Fees $3,426 - $ -
Natural Gas $33,874 4,321 MMBtu $7.84
LPG $13,597 827 MMBtu $16.44
TOTAL ENERGY COSTS $197,898
RECOMMENDED SAVINGS* $97,370 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,930
#|Description Savings
Cost
Status Electricity Usage Personnel Changes Administrative Changes Electricity Usage Personnel Changes Administrative Changes
$ kWh $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$7,830
Cost:
$8,000
$7,830 124,000 - - - - $7,830
124,000
kWh
-
-
$
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,100
Cost:
$2,600
$1,100 18,200 - - - - $1,100
18,200
kWh
-
-
$
-
-
$
03: 4.423 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$88,440
Cost:
$400
- - $64,800 - $23,640 - -
-
kWh
$64,800
-
$
$23,640
-
$
TOTAL RECOMMENDED Savings:
$97,370
Cost:
$11,000
$8,930 142,200 $64,800 - $23,640 - $8,930
142,200
kWh
$64,800
-
$
$23,640
-
$
TOTAL IMPLEMENTED Savings:
$8,930
Cost:
$10,600
$8,930 142,200 - - - - $8,930
142,200
kWh
-
-
$
-
-
$
Savings
Cost
$ kWh $ $ $ $
Electricity Usage Personnel Changes Administrative Changes Electricity Usage Personnel Changes Administrative Changes