IAC Assessment: OR0477
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0477
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2005
Principal Product Frozen Foods
NAICS 424420 - Packaged Frozen Food Merchant Wholesalers
SIC 5142 - Packaged Frozen Foods
Sales $100,000,000-$500,000,000
# of Employees 280
Plant Area (Sq.Ft.) 225,000
Annual Production 400,000,000 Pounds
Production Hrs. Annual 5,376
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $705,221 47,014,720 kWh $0.02
Electricity Demand $461,601 115,604 kW-months/year $3.99
Electricity Fees $146,111 - $ -
Natural Gas $518,339 912,754 MMBtu $0.57
TOTAL ENERGY COSTS $2,872,126
RECOMMENDED SAVINGS* $434,381 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $123,966
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ Tgal $ $
01: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$240,000
Cost:
$250,000
- - - - - - - - - - $240,000 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
$240,000
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$34,000
Cost:
$34,000
- - - - $34,000 - - - - - - - -
-
kWh
-
-
kW-months/year
$34,000
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$28,455
Cost:
$11,500
- - - - - - $28,455 52,633 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$28,455
52,633
MMBtu
-
-
Tgal
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$18,900
Cost:
$3,100
$12,600 641,900 $6,300 220 - - - - - - - - $12,600
641,900
kWh
$6,300
220
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
05: 3.7211 MODIFY MATERIAL APPLICATION METHODS Savings:
$14,995
Cost:
$1,875
- - - - - - $12,570 23,250 $2,425 6,477,680 - - -
-
kWh
-
-
kW-months/year
-
-
$
$12,570
23,250
MMBtu
$2,425
6,477,680
Tgal
-
-
$
06: 3.5311 RECOVER AND REUSE WASTE MATERIAL Savings:
$13,416
Cost:
$25,000
- - - - - - - - $13,416 35,839,672 - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$13,416
35,839,672
Tgal
-
-
$
07: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL Savings:
$29,545
Cost:
$182,000
$28,645 1,909,680 $900 218 - - - - - - - - $28,645
1,909,680
kWh
$900
218
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
08: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$48,200
Cost:
-
$48,200 2,049,900 - - - - - - - - - - $48,200
2,049,900
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$6,870
Cost:
$84,875
$6,870 295,400 - - - - - - - - - - $6,870
295,400
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$434,381
Cost:
$592,350
$96,315 4,896,880 $7,200 438 $34,000 - $41,025 75,883 $15,841 42,317,352 $240,000 - $96,315
4,896,880
kWh
$7,200
438
kW-months/year
$34,000
-
$
$41,025
75,883
MMBtu
$15,841
42,317,352
Tgal
$240,000
-
$
TOTAL IMPLEMENTED Savings:
$123,966
Cost:
$41,475
$60,800 2,691,800 $6,300 220 - - $41,025 75,883 $15,841 42,317,352 - - $60,800
2,691,800
kWh
$6,300
220
kW-months/year
-
-
$
$41,025
75,883
MMBtu
$15,841
42,317,352
Tgal
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ Tgal $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Water Disposal Personnel Changes