Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2010
Principal Product Remanufactured Lumber Products
NAICS 321911 - Wood Window and Door Manufacturing
SIC 2431 - Millwork
Sales $10,000,000-$50,000,000
# of Employees 70
Plant Area (Sq.Ft.) 141,530
Annual Production 1 Units
Production Hrs. Annual 2,250
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $124,881 2,392,075 kWh $0.05
Electricity Demand $73,741 15,533 kW-months/year $4.75
Electricity Fees $36,543 - $ -
Natural Gas $38,267 3,898 MMBtu $9.82
LPG $16,545 986 MMBtu $16.78
TOTAL ENERGY COSTS $289,977
RECOMMENDED SAVINGS* $17,678 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,086
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$8,447
Cost:
$2,500
$8,447 163,200 - - - - $8,447
163,200
kWh
-
-
kW-months/year
-
-
MMBtu
02: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL Savings:
$6,592
Cost:
$14,997
- - - - $6,592 693 -
-
kWh
-
-
kW-months/year
$6,592
693
MMBtu
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,447
Cost:
$2,724
- - - - $1,447 152 -
-
kWh
-
-
kW-months/year
$1,447
152
MMBtu
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,192
Cost:
-
$721 14,933 $471 107 - - $721
14,933
kWh
$471
107
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$17,678
Cost:
$20,221
$9,168 178,133 $471 107 $8,039 845 $9,168
178,133
kWh
$471
107
kW-months/year
$8,039
845
MMBtu
TOTAL IMPLEMENTED Savings:
$11,086
Cost:
$5,224
$9,168 178,133 $471 107 $1,447 152 $9,168
178,133
kWh
$471
107
kW-months/year
$1,447
152
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas