Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2012
Principal Product I joists
NAICS 321213 - Engineered Wood Member (except Truss) Manufacturing
SIC 2439 - Structural Wood Members, Nec
Sales $100,000,000-$500,000,000
# of Employees 110
Plant Area (Sq.Ft.) 275,000
Annual Production 365,000,000 Units
Production Hrs. Annual 2,080
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $412,076 8,213,600 kWh $0.05
Electricity Demand $215,687 35,712 kW-months/year $6.04
Natural Gas $67,598 7,417 MMBtu $9.11
TOTAL ENERGY COSTS $695,361
RECOMMENDED SAVINGS* $52,304 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.1231 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS Savings:
$720
Cost:
$500
- - - - $720 139 - - - - -
-
kWh
-
-
kW-months/year
$720
139
MMBtu
-
-
$
-
-
$
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$25,857
Cost:
$33,400
$27,122 525,120 $(-1,265) (-202) - - - - - - $27,122
525,120
kWh
$(-1,265)
(-202)
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,291
Cost:
$23,135
$9,585 185,585 $(-111) (-18) - - $246 - $1,571 - $9,585
185,585
kWh
$(-111)
(-18)
kW-months/year
-
-
MMBtu
$246
-
$
$1,571
-
$
04: 2.5121 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH Savings:
$14,435
Cost:
$34,000
$17,135 331,760 $(-2,700) (-432) - - - - - - $17,135
331,760
kWh
$(-2,700)
(-432)
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$52,304
Cost:
$91,035
$53,843 1,042,465 $(-4,077) (-652) $720 139 $246 - $1,571 - $53,843
1,042,465
kWh
$(-4,077)
(-652)
kW-months/year
$720
139
MMBtu
$246
-
$
$1,571
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost