IAC Assessment: OR0609
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0609
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2013
Principal Product Freeze Dried Foods
NAICS 311411 - Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2037 - Frozen Fruits And Vegetables
Sales $50,000,000-$100,000,000
# of Employees 385
Plant Area (Sq.Ft.) 207,119
Annual Production 8,453 Pieces
Production Hrs. Annual 8,760
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $926,908 20,628,000 kWh $0.04
Electricity Demand $285,246 36,656 kW-months/year $7.78
Electricity Fees $71,581 - $ -
Natural Gas $386,171 85,048 MMBtu $4.54
TOTAL ENERGY COSTS $1,919,176
RECOMMENDED SAVINGS* $324,584 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $117,782
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
01: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER Savings:
$13,082
Cost:
$4,037
- - - - $13,082 3,122 - - - - -
-
kWh
-
-
kW-months/year
$13,082
3,122
MMBtu
-
-
Tgal
-
-
$
02: 2.2511 INSULATE BARE EQUIPMENT Savings:
$4,347
Cost:
$4,299
- - - - $4,347 1,038 - - - - -
-
kWh
-
-
kW-months/year
$4,347
1,038
MMBtu
-
-
Tgal
-
-
$
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$3,555
Cost:
$4,200
$3,555 75,006 - - - - - - - - $3,555
75,006
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
04: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY Savings:
$6,499
Cost:
$5,792
$4,002 84,424 - - $2,497 596 - - - - $4,002
84,424
kWh
-
-
kW-months/year
$2,497
596
MMBtu
-
-
Tgal
-
-
$
05: 2.2492 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR Savings:
$4,900
Cost:
$4,480
$4,900 103,379 - - - - - - - - $4,900
103,379
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
06: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$142,102
Cost:
$374,500
$(-7,723) (-162,936) $(-1,801) (-223) - - $153,976 15,190 $(-2,350) - $(-7,723)
(-162,936)
kWh
$(-1,801)
(-223)
kW-months/year
-
-
MMBtu
$153,976
15,190
Tgal
$(-2,350)
-
$
07: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$117,782
Cost:
$160,770
$117,782 2,484,792 - - - - - - - - $117,782
2,484,792
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,018
Cost:
$5,875
$4,018 84,765 - - - - - - - - $4,018
84,765
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
09: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$28,299
Cost:
$42,000
$22,947 484,108 $5,352 663 - - - - - - $22,947
484,108
kWh
$5,352
663
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$324,584
Cost:
$605,953
$149,481 3,153,538 $3,551 440 $19,926 4,756 $153,976 15,190 $(-2,350) - $149,481
3,153,538
kWh
$3,551
440
kW-months/year
$19,926
4,756
MMBtu
$153,976
15,190
Tgal
$(-2,350)
-
$
TOTAL IMPLEMENTED Savings:
$117,782
Cost:
$160,770
$117,782 2,484,792 - - - - - - - - $117,782
2,484,792
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Ancillary Material Cost