IAC logo
IAC Assessment: OR0628
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0628
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2014
Principal Product moulding
NAICS 321213 - Engineered Wood Member (except Truss) Manufacturing
SIC 2431 - Millwork
Sales $1,000,000-$5,000,000
# of Employees 34
Plant Area (Sq.Ft.) 65,000
Annual Production 150,000 Units
Production Hrs. Annual 1,550
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $86,194 1,573,920 kWh $0.05
Electricity Demand $86,289 10,526 kW-months/year $8.20
Electricity Fees $20,550 - $ -
TOTAL ENERGY COSTS $193,033
RECOMMENDED SAVINGS* $110,707 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,718
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
01: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$44,216
Cost:
$17,353
$35,615 643,770 $26,854 3,173 $(-20,003) (-2,746) - - - - $1,750 - $35,615
643,770
kWh
$26,854
3,173
kW-months/year
$(-20,003)
(-2,746)
MMBtu
-
-
$
-
-
$
$1,750
-
$
02: 2.2515 USE OPTIMUM THICKNESS INSULATION Savings:
$3,869
Cost:
$828
$3,869 70,004 - - - - - - - - - - $3,869
70,004
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
03: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES Savings:
$3,198
Cost:
-
- - - - - - - - $3,198 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$3,198
-
$
-
-
$
04: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$25,006
Cost:
$4,810
$9,372 169,411 $15,634 1,848 - - - - - - - - $9,372
169,411
kWh
$15,634
1,848
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,875
Cost:
$1,293
$1,043 18,860 $1,334 158 - - - - $49 - $449 - $1,043
18,860
kWh
$1,334
158
kW-months/year
-
-
MMBtu
-
-
$
$49
-
$
$449
-
$
06: 2.4325 UPGRADE CONVEYORS Savings:
$20,000
Cost:
$11,206
- - - - - - $20,000 - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$20,000
-
$
-
-
$
-
-
$
07: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$9,718
Cost:
$2,460
$9,718 175,729 - - - - - - - - - - $9,718
175,729
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$877
Cost:
$500
$527 9,532 $350 41 - - - - - - - - $527
9,532
kWh
$350
41
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
09: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT Savings:
$948
Cost:
$676
$1,126 20,362 $(-178) (-21) - - - - - - - - $1,126
20,362
kWh
$(-178)
(-21)
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$110,707
Cost:
$39,126
$61,270 1,107,668 $43,994 5,199 $(-20,003) (-2,746) $20,000 - $3,247 - $2,199 - $61,270
1,107,668
kWh
$43,994
5,199
kW-months/year
$(-20,003)
(-2,746)
MMBtu
$20,000
-
$
$3,247
-
$
$2,199
-
$
TOTAL IMPLEMENTED Savings:
$9,718
Cost:
$2,460
$9,718 175,729 - - - - - - - - - - $9,718
175,729
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Administrative Changes Ancillary Material Cost