Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2015 |
Principal Product | X-Ray Film |
NAICS | 325992 - Photographic Film, Paper, Plate, and Chemical Manufacturing |
SIC | 3861 - Photographic Equipment And Supplies |
Sales | $1,000,000-$5,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 237,000 |
Annual Production | 5,028 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,421,422 | 29,748,600 | kWh | $0.05 |
Electricity Demand | $423,116 | 49,390 | kW-months/year | $8.57 |
Electricity Fees | $71,308 | - | $ | - |
Natural Gas | $1,195,183 | 244,019 | MMBtu | $4.90 |
TOTAL ENERGY COSTS | $3,111,029 | |||
RECOMMENDED SAVINGS* | $422,879 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $329,244 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION |
Savings: $58,422 Cost: $9,638 |
- | - | - | - | $58,422 | 13,158 | - | - |
- - kWh |
- - kW-months/year |
$58,422 13,158 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $270,822 Cost: $210,050 |
$129,268 | 2,734,104 | $36,529 | 4,264 | - | - | $105,025 | - |
$129,268 2,734,104 kWh |
$36,529 4,264 kW-months/year |
- - MMBtu |
$105,025 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $93,635 Cost: $132,280 |
- | - | - | - | $93,635 | 21,089 | - | - |
- - kWh |
- - kW-months/year |
$93,635 21,089 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $422,879 Cost: $351,968 |
$129,268 | 2,734,104 | $36,529 | 4,264 | $152,057 | 34,247 | $105,025 | - | $129,268 2,734,104 kWh |
$36,529 4,264 kW-months/year |
$152,057 34,247 MMBtu |
$105,025 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $329,244 Cost: $219,688 |
$129,268 | 2,734,104 | $36,529 | 4,264 | $58,422 | 13,158 | $105,025 | - | $129,268 2,734,104 kWh |
$36,529 4,264 kW-months/year |
$58,422 13,158 MMBtu |
$105,025 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost |