Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2015 |
Principal Product | Crossarms |
NAICS | 321999 - All Other Miscellaneous Wood Product Manufacturing |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | $10,000,000-$50,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 435,600 |
Annual Production | 15,000 Thousand Feet |
Production Hrs. Annual | 6,552 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $84,731 | 1,392,680 | kWh | $0.06 |
Electricity Demand | $58,520 | 8,072 | kW-months/year | $7.25 |
Electricity Fees | $3,963 | - | $ | - |
Natural Gas | $33,868 | 3,378 | MMBtu | $10.03 |
TOTAL ENERGY COSTS | $181,082 | |||
RECOMMENDED SAVINGS* | $34,376 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,318 Cost: $1,010 |
- | - | - | - | $1,318 | 138 | - | - |
- - kWh |
- - kW-months/year |
$1,318 138 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $11,122 Cost: $6,541 |
- | - | - | - | $11,122 | 1,165 | - | - |
- - kWh |
- - kW-months/year |
$11,122 1,165 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2162 REDUCE EXCESS STEAM BLEEDING |
Savings: $1,876 Cost: $1,768 |
- | - | - | - | $1,876 | 196 | - | - |
- - kWh |
- - kW-months/year |
$1,876 196 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,563 Cost: $63,189 |
$10,486 | 172,352 | $4,761 | 657 | - | - | $316 | - |
$10,486 172,352 kWh |
$4,761 657 kW-months/year |
- - MMBtu |
$316 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $4,497 Cost: $24,955 |
$2,096 | 34,447 | $2,401 | 331 | - | - | - | - |
$2,096 34,447 kWh |
$2,401 331 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,376 Cost: $97,463 |
$12,582 | 206,799 | $7,162 | 988 | $14,316 | 1,499 | $316 | - | $12,582 206,799 kWh |
$7,162 988 kW-months/year |
$14,316 1,499 MMBtu |
$316 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |