Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2016 |
Principal Product | Hardboards |
NAICS | 321219 - Reconstituted Wood Product Manufacturing |
SIC | 2493 - Reconstituted Wood Products |
Sales | $5,000,000-$10,000,000 |
# of Employees | 191 |
Plant Area (Sq.Ft.) | 2,744,280 |
Annual Production | 1,400,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,758,138 | 31,061,180 | kWh | $0.06 |
Electricity Demand | $232,961 | 72,540 | kW-months/year | $3.21 |
Electricity Fees | $129,164 | - | $ | - |
Wood | $414,656 | 251,073 | MMBtu | $1.65 |
TOTAL ENERGY COSTS | $2,534,919 | |||
RECOMMENDED SAVINGS* | $91,165 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,507 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Wood | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Wood | Personnel Changes | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.5121 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH |
Savings: $2,739 Cost: - |
$2,242 | 33,224 | - | - | - | - | - | - | $497 | - | - | - |
$2,242 33,224 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$497 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,310 Cost: $2,584 |
- | - | - | - | $1,310 | 556 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,310 556 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $12,507 Cost: $32,393 |
$11,028 | 187,450 | $1,193 | 360 | - | - | $693 | - | - | - | $(-407) | - |
$11,028 187,450 kWh |
$1,193 360 kW-months/year |
- - MMBtu |
$693 - $ |
- - $ |
$(-407) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4325 UPGRADE CONVEYORS |
Savings: $74,609 Cost: $242,718 |
$66,035 | 1,122,475 | $8,574 | 2,590 | - | - | - | - | - | - | - | - |
$66,035 1,122,475 kWh |
$8,574 2,590 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $91,165 Cost: $277,695 |
$79,305 | 1,343,149 | $9,767 | 2,950 | $1,310 | 556 | $693 | - | $497 | - | $(-407) | - | $79,305 1,343,149 kWh |
$9,767 2,950 kW-months/year |
$1,310 556 MMBtu |
$693 - $ |
$497 - $ |
$(-407) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,507 Cost: $32,393 |
$11,028 | 187,450 | $1,193 | 360 | - | - | $693 | - | - | - | $(-407) | - | $11,028 187,450 kWh |
$1,193 360 kW-months/year |
- - MMBtu |
$693 - $ |
- - $ |
$(-407) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Wood | Personnel Changes | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Wood | Personnel Changes | Administrative Changes | Primary Raw Material |