Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2016 |
Principal Product | Plastic Containers |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 96,000 |
Annual Production | 40,000,000 Units |
Production Hrs. Annual | 6,240 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $192,640 | 4,676,630 | kWh | $0.04 |
Electricity Demand | $94,920 | 12,656 | kW-months/year | $7.50 |
Electricity Fees | $1,200 | - | $ | - |
Natural Gas | $839 | 27 | MMBtu | $31.07 |
TOTAL ENERGY COSTS | $289,599 | |||
RECOMMENDED SAVINGS* | $268,278 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,581 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $157,793 Cost: $301,613 |
$1,825 | 44,306 | $1,370 | 183 | - | - | - | - | $154,598 | - |
$1,825 44,306 kWh |
$1,370 183 kW-months/year |
- - $ |
- - $ |
$154,598 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $102,571 Cost: $10,390 |
$20,162 | 489,494 | - | - | - | - | - | - | $82,409 | - |
$20,162 489,494 kWh |
- - kW-months/year |
- - $ |
- - $ |
$82,409 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,333 Cost: $229 |
$4,333 | 105,185 | - | - | - | - | - | - | - | - |
$4,333 105,185 kWh |
- - kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,117 Cost: $5,344 |
$1,690 | 41,034 | $592 | 79 | $482 | - | $(-647) | - | - | - |
$1,690 41,034 kWh |
$592 79 kW-months/year |
$482 - $ |
$(-647) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,464 Cost: - |
$1,082 | 26,279 | $382 | 51 | - | - | - | - | - | - |
$1,082 26,279 kWh |
$382 51 kW-months/year |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $268,278 Cost: $317,576 |
$29,092 | 706,298 | $2,344 | 313 | $482 | - | $(-647) | - | $237,007 | - | $29,092 706,298 kWh |
$2,344 313 kW-months/year |
$482 - $ |
$(-647) - $ |
$237,007 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,581 Cost: $5,344 |
$2,772 | 67,313 | $974 | 130 | $482 | - | $(-647) | - | - | - | $2,772 67,313 kWh |
$974 130 kW-months/year |
$482 - $ |
$(-647) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Administrative Changes | Ancillary Material Cost | Primary Product |