IAC Assessment: OR0692
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0692
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2017
Principal Product Fabricated Metal Structures
NAICS 332312 - Fabricated Structural Metal Manufacturing
SIC 3441 - Fabricated Structural Metal
Sales $100,000,000-$500,000,000
# of Employees 350
Plant Area (Sq.Ft.) 2,309,000
Annual Production 15 Units
Production Hrs. Annual 8,760
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $177,965 2,518,252 kWh $0.07
Electricity Demand $33,999 7,010 kW-months/year $4.85
Electricity Fees $10,856 - $ -
TOTAL ENERGY COSTS $222,820
RECOMMENDED SAVINGS* $30,736 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Primary Raw Material One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Primary Raw Material One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.5123 REDUCE FLUID FLOW RATES Savings:
$26,801
Cost:
$7,395
$26,801 379,236 - - - - - - $26,801
379,236
kWh
-
-
kW-months/year
-
-
$
-
-
$
02: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD Savings:
$2,636
Cost:
$3,060
$136 1,921 - - - - $2,500 - $136
1,921
kWh
-
-
kW-months/year
-
-
$
$2,500
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,299
Cost:
$3,670
$700 9,899 $132 27 $302 - $165 - $700
9,899
kWh
$132
27
kW-months/year
$302
-
$
$165
-
$
TOTAL RECOMMENDED Savings:
$30,736
Cost:
$14,125
$27,637 391,056 $132 27 $302 - $2,665 - $27,637
391,056
kWh
$132
27
kW-months/year
$302
-
$
$2,665
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Primary Raw Material One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Primary Raw Material One-time Revenue or Avoided Cost