IAC Assessment: OR0708
Sponsored by:
EERE AMO
IAC logo
IAC Assessment: OR0708
IAC Center Oregon State University
Assessment Year 2018
Principal Product Dimensional Lumber
NAICS 321113 - Sawmills
SIC 2421 - Sawmills And Planing Mills, General
Sales $10,000,000-$50,000,000
# of Employees 95
Plant Area (Sq.Ft.) 6,970,000
Annual Production 64,000 Units
Production Hrs. Annual 8,760
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $405,091 7,581,620 kWh $0.05
Electricity Demand $253,585 33,103 kW-months/year $7.66
Natural Gas $65,323 23,874 MMBtu $2.74
TOTAL ENERGY COSTS $723,999
RECOMMENDED SAVINGS* $59,366 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.4131 REPLACE OVER-SIZE MOTORS AND PUMPS WITH OPTIMUM SIZE Savings:
$40,920
Cost:
$18,036
$37,223 487,405 $3,697 573 $37,223
487,405
kWh
$3,697
573
kW-months/year
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$12,870
Cost:
$46,694
- - $12,870 1,650 -
-
kWh
$12,870
1,650
kW-months/year
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,132
Cost:
-
$826 14,204 $1,306 142 $826
14,204
kWh
$1,306
142
kW-months/year
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$3,444
Cost:
$8,480
$1,732 29,766 $1,712 186 $1,732
29,766
kWh
$1,712
186
kW-months/year
TOTAL RECOMMENDED Savings:
$59,366
Cost:
$73,210
$39,781 531,375 $19,585 2,551 $39,781
531,375
kWh
$19,585
2,551
kW-months/year
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand