IAC Assessment: ORS001
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ORS001
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1999
Principal Product Processed fish products
NAICS n/a
SIC 2091 - Canned And Cured Fish And Seafoods
Sales $10,000,000-$50,000,000
# of Employees 75
Plant Area (Sq.Ft.) 20,000
Annual Production 18,000,000 Pounds
Production Hrs. Annual 3,300
Location (State) AK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $273,231 2,449,297 kWh $0.11
Electricity Demand $55,076 94,416 kW-months/year $0.58
Electricity Fees $15,393 - $ -
Fuel Oil #2 $155,370 23,140 MMBtu $6.71
TOTAL ENERGY COSTS $529,821
RECOMMENDED SAVINGS* $702,733 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,049
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Fuel Oil #2 Personnel Changes Water Consumption Electricity Usage Electricity Demand Electricity Fees Fuel Oil #2 Personnel Changes Water Consumption
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ Tgal
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$79,500
Cost:
$30,000
$100,700 1,095,838 $24,600 3,600 - - $(-35,800) (-6,599) $(-10,000) - - - $100,700
1,095,838
kWh
$24,600
3,600
kW-months/year
-
-
$
$(-35,800)
(-6,599)
MMBtu
$(-10,000)
-
$
-
-
Tgal
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$6,484
Cost:
$6,000
- - - - $6,484 - - - - - - - -
-
kWh
-
-
kW-months/year
$6,484
-
$
-
-
MMBtu
-
-
$
-
-
Tgal
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$7,190
Cost:
$10,700
$5,700 54,807 $1,490 130 - - - - - - - - $5,700
54,807
kWh
$1,490
130
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
Tgal
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,400
Cost:
$16,800
$2,400 23,154 - - - - - - - - - - $2,400
23,154
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
Tgal
05: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$6,070
Cost:
-
$6,070 58,324 - - - - - - - - - - $6,070
58,324
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
Tgal
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,829
Cost:
$700
- - - - - - $1,829 272 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,829
272
MMBtu
-
-
$
-
-
Tgal
07: 4.4450 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$519,000
Cost:
$250,000
- - - - - - - - $519,000 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$519,000
-
$
-
-
Tgal
08: 4.1110 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$78,300
Cost:
$175,000
$700 5,862 - - - - - - $77,600 - - - $700
5,862
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$77,600
-
$
-
-
Tgal
09: 3.4151 MINIMIZE WATER USAGE Savings:
$1,960
Cost:
-
- - - - - - - - - - $1,960 - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
$1,960
-
Tgal
TOTAL RECOMMENDED Savings:
$702,733
Cost:
$489,200
$115,570 1,237,985 $26,090 3,730 $6,484 - $(-33,971) (-6,327) $586,600 - $1,960 - $115,570
1,237,985
kWh
$26,090
3,730
kW-months/year
$6,484
-
$
$(-33,971)
(-6,327)
MMBtu
$586,600
-
$
$1,960
-
Tgal
TOTAL IMPLEMENTED Savings:
$17,049
Cost:
$11,400
$11,770 113,131 $1,490 130 - - $1,829 272 - - $1,960 - $11,770
113,131
kWh
$1,490
130
kW-months/year
-
-
$
$1,829
272
MMBtu
-
-
$
$1,960
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ Tgal
Electricity Usage Electricity Demand Electricity Fees Fuel Oil #2 Personnel Changes Water Consumption Electricity Usage Electricity Demand Electricity Fees Fuel Oil #2 Personnel Changes Water Consumption