Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Rutgers, State Univ. of NJ |
---|---|
Assessment Year | 1987 |
Principal Product | THERMOPLASTIC EXTRUSION |
NAICS | n/a |
SIC | 3083 - Laminated Plastics Plate & Sheet |
Sales | $5,000,000-$10,000,000 |
# of Employees | 105 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 53,000,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $136,003 | 1,987,104 | kWh | $0.07 |
Natural Gas | $21,723 | 3,879 | MMBtu | $5.60 |
TOTAL ENERGY COSTS | $157,726 | |||
RECOMMENDED SAVINGS* | $14,395 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,105 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,628 Cost: $376 |
$2,628 | 38,687 |
$2,628 38,687 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2514 COVER OPEN TANKS |
Savings: $3,290 Cost: $200 |
$3,290 | 48,066 |
$3,290 48,066 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $822 Cost: $31 |
$822 | 12,016 |
$822 12,016 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $4,104 Cost: - |
$4,104 | 60,375 |
$4,104 60,375 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,551 Cost: - |
$3,551 | 51,876 |
$3,551 51,876 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $14,395 Cost: $607 |
$14,395 | 211,020 | $14,395 211,020 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,105 Cost: $407 |
$11,105 | 162,954 | $11,105 162,954 kWh |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Usage |